  • Question 501:

    Which is a type of issue?

    A. An expected dis-benefit

    B. An off-specification

    C. Aproject outcome

    D. A scope tolerance

  • Question 502:

    If a project's benefit tolerance is forecast to be exceeded, to whom should this be escalated to for a decision?

    A. Senior User

    B. Executive

    C. Corporate/programme management

    D. Senior Supplier

  • Question 503:

    Which of the following statements about the Project Initiation Documentation are true?

    1.

    The Project Initiation Documentation is used to ensure that a sound basis exists exists before the Project Board authorizes a project.

    2.

    The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project before the Project Board authorizes a project.

    A. Only 1 is true

    B. Only 2 is true

    C. Both 1 and 2 are true

    D. Neither 1 or 2 are true

  • Question 504:

    Which is a responsibility of a risk owner?

    A. Identify risks to the project that might occur in their department

    B. Own and authorize theuse of the risk budget to fund risk responses

    C. Manage, monitor and control all aspects of an assigned risk

    D. Determine project risk appetite

  • Question 505:

    Which of the following statements about the Closing a Project process are true?

    1.

    The Closing a Project process provides a fixed point for the receipt of completed Work Packages for the work performed in the final stage.

    2.

    The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved. Packages for the work performed in the final stage.

    A. Only 1 is true

    B. Only 2 is true

    C. Both 1 and 2 aretrue

    D. Neither 1 or 2 are true

  • Question 506:

    Which is a purpose of the Project Product Description?

    A. Define the key responsibilities for delivering product quality

    B. Provide information about the state of products

    C. Define the quality anticipated by the customer

    D. Provide product cost input tothe Business Case

  • Question 507:

    Which is NOT an objective of the Controlling a Stage process?

    A. Implement actions to control the impact of risks that occur during the stage

    B. Review the Business Case at regular intervalsto assess the impact of changes that occur during the stage

    C. Update the Business Case with any changes agreed with the Project Board

    D. Coordinate the delivery of products as agreed in the Stage Plan

  • Question 508:

    Where should an off-specification be recorded?

    A. Risk Register

    B. Issue Register

    C. Work Package

    D. Configuration Management Strategy

  • Question 509:

    Which process provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification?

    A. Controlling a Stage

    B. Closing a Project

    C. Directing a Project

    D. Managing a Stage Boundary

  • Question 510:

    Which statement describes the Implement' step within the recommended risk management procedure?

    A. Take planned action to respond to a risk

    B. Implement the responsibilities for risks defined in the Risk Management Strategy

    C. Assess the proximity of a risk

    D. Identify the level of risks that can be tolerated by the project

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.