Which is a task of product-based planning?
A. Design the plan
B. Create the product flow diagram
C. Analyze the risks
D. Prepare the schedule
Which product identifies the management stages and timescales of a project?
A. Project Brief
B. Project Product Description
C. Project Plan
D. Initiation Stage Plan
Which is an objective of the quality review technique?
A. To baseline a product
B. To provide a common understanding of what products a project will create
C. To define the quality methods required within a project
D. To determine the quality responsibilities of a project team
Which of the following statements about lines of authority and reporting are true?
1.
The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.
2.
If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager down by the Project Board.
A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Neither 1 or 2 are true
Which process provides the Project Board with the information it requires in order to commit resources to the project?
A. Managing Product Delivery
B. Initiating a Project
C. Controlling a Stage
D. Directinga Project
Where should a Team Manager look for information on the quality required for a product?
A. Project Initiation Documentation
B. Product Description
C. Team Plan
D. Quality Management Strategy
Upon what environment is PRINCE2 based?
A. Operational
B. Configuration
C. Programme
D. Customer/supplier
Which is a purpose of the Managing Product Delivery process?
A. Enable the Senior Supplier to be provided with sufficient information by the Project Manager so that they can review the success of the current Work Package
B. Provide a controlled link between the Project Manager and the Team Manager(s)
C. Enable the Project Board to requestupdates to the current Team Plan
D. Establish solid foundations for the project
If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?
A. Checkpoint Report
B. Highlight Report
C. Issue Report
D. Product Status Account
Which is the purpose of the Change theme?
A. Prevent change to baselined products
B. Identify, assess and control any potential and approved changes to baselined products
C. Establish mechanisms to monitor and compare actual achievements against those planned
D. Assess and control uncertainty
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.