  • Question 571:

    Which provides a single source of reference that may be used by people joining a project after it has been initiated so they can quickly and easily find out how the project is being managed?

    A. Project Brief

    B. Project Initiation Documentation

    C. Project mandate

    D. Project Product Description

  • Question 572:

    What process is used by the Project Board to respond to an Exception Report?

    A. Controlling a Stage

    B. Managing a Stage Boundary

    C. Managing Product Delivery

    D. Directing a Project

  • Question 573:

    Identify the missing words in the following sentence. An objective of the Directing a Project process is to [?] throughout a project's life,

    A. document how risks will bemanaged

    B. identify who will be responsible for quality

    C. provide management direction and control

    D. define the benefits to be realized

  • Question 574:

    Which statement about stages is true?

    A. Management stages should be of the same duration

    B. The use of technical stages is mandatory

    C. The use of management stages is mandatory

    D. Management stages are driven by specialist teams

  • Question 575:

    Identify the missing words in the following sentence.During the Initiating a Project process the [?] before a project is authorized.

    A. minimum necessaryis done to decide if a project is worthwhile

    B. aim is to establish sound foundations to achieve a successful project

    C. Project Brief is assembled and approved

    D. project approach appropriate for delivering a project is selected

  • Question 576:

    How many tasks does the product-based planning technique describe?

    A. One

    B. Two

    C. Three

    D. Four

  • Question 577:

    Which product summarizes progress and is used to decide whether to amend the project scope or stop the project?

    A. Checkpoint Report

    B. End Stage Report

    C. End Project Report

    D. Product Status Account

  • Question 578:

    Which is a purpose of a Product Description?

    A. Provide the cost tolerance available for individual products

    B. Define reporting frequency

    C. Record the quality checks completed for the End Stage Report

    D. Document the level of quality required of a product

  • Question 579:

    What is documented in the project plan to support the 'manage by exception' principle?

    A. The project's tolerances for cost and time

    B. A project product's quality criteria

    C. The expected project benefits

    D. Activities to mitigate project risks

  • Question 580:

    Which is an assumption about the PRINCE2 customer/supplier environment?

    A. The supplier will pay for the project

    B. The customer will provide the resources to deliver the products

    C. The customer will specify the desired result

    D. The supplier will tailor the project's application of PRINCE2

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.