Why can PRINCE2 be applied to any type of project?
A. Because it provides the project manager with procedures for managing project risks and issues
B. Because it allows each member of the project management team to fully understand their role and responsibilities
C. Because it separates the management of the project from the specialist work needed to deliver the products
D. Because it provides the project manager with a planning procedure to plan the project more effectively
Which is a key decision made during the 'directing a project' process?
A. Select and appoint the project executive
B. Approve the project manager role description
C. Confirm that the benefits management approach addresses all expected benefits
D. Approve the proposed project mandate
Identify the missing words in the following sentence.
When proposed changes [ ? ], the change authority must refer the decision back to the project board.
A. are below the agreed change budget
B. are objected to by team members
C. are rejected by the change authority
D. exceed the agreed change budget
How is the tailoring approach defined for a project?
A. The project board approves the approach
B. The project board documents the approach
C. Project assurance approves the approach
D. Project assurance documents the approach
Which is a purpose of the 'initiating a project' process?
A. To ensure the project has a sound basis before asking the project board to authorize the project
B. To authorize the stage plan for the next management stage of the project
C. To establish a contract between the project management team and the commissioning organization
D. To ensure that prerequisites are in place before starting the project
Which statement describes the context of the 'initiating a project" process?
A. The project is viewed from the perspective of the project board in this process
B. This process should result in key stakeholders being committed to the project
C. This process is triggered by the assembly of the project brief
D. The 'controlling a stage' process will start immediately after this process
Which control must be used as a minimum requirement for applying the 'progress' theme?
A. A project plan
B. Tolerances
C. An Issue register
D. Highlight reports
Which theme establishes the mechanisms to control against baselines by providing a forecast for the project's objectives and continued viability?
A. Business case
B. Plans
C. Change
D. Progress
Which statement about the length of management stages in a project is CORRECT?
A. A higher level of major risk will require a stage to be longer
B. Stage length is influenced by project board availability
C. A higher level of major risk will require a stage to be shorter
D. Use of management stages represents a time driven control
Which is part of quality control?
A. Undertaking quality reviews
B. Writing product descriptions
C. Providing assurance that the project is being conducted properly
D. Documenting the customer's quality expectations
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.