Which is a purpose of the 'initiating a project' process?
A. To decide if it is worthwhile to initiate a project
B. To decide on the project approach
C. To establish solid foundations for a project
D. To identify the number of work packages required
Identify the missing words in the following sentence.
The 'directing a project' process starts when [ ? ] and is triggered by the request to initiate a project.
A. the 'starting up a project' process is completed
B. the project mandate has been approved by the project board
C. the project board has agreed the project strategies
D. corporate, programme management or the customer have authorized a project
Which process ensures focus on the delivery of a stage's products and avoids uncontrolled change?
A. Directing a project
B. Managing a stage boundary
C. Controlling a stage
D. Starting up a project
What is the project manager role responsible for?
A. Approving the completion of each management stage
B. Ensuring that the project produces the required products
C. Defining the project-level tolerances
D. Verifying that the project gives value for money
Which is a minimum requirement for applying the quality theme?
A. To use lessons to inform quality planning
B. To use the prescribed approach to quality management
C. To use external quality standards for quality control
D. To use user stories to inform the project product description
Which product is created in the 'starting up a project' process to define and confirm the scope of the project?
A. Project mandate
B. Initiation stage plan
C. Project initiation documentation
D. Project brief
Which theme provides all management levels within the project management team with mechanisms for monitoring and control?
A. Progress
B. Change
C. Organization
D. Quality
Which is a purpose of a quality register?
A. To record the quality management approach for a product
B. To issue a unique number for each product
C. To detail the number and type of quality activities to be conducted
D. To identify corrective actions that are required after an audit by quality assurance
Which describes a characteristic of a project?
A. It maintains business as usual profitability
B. It provides a quality service to customers
C. It involves a team with different skills
D. It enables established and proven best practices
What action is taken as part of the 'controlling a stage' process?
1.
Create an exception plan
2.
Authorize work to be done
3.
Take corrective action
4.
Obtain approvals for completed products
A. 1 and 2
B. 2 and 3
C. 3 and 4
D. 1 and 4
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.