Exam Details

  • Exam Code
    :PRINCE2-PRACTITIONER
  • Exam Name
    :PRINCE2 Practitioner
  • Certification
    :PRINCE2 Certifications
  • Vendor
    :PRINCE2
  • Total Questions
    :328 Q&As
  • Last Updated
    :Apr 15, 2025

PRINCE2 PRINCE2 Certifications PRINCE2-PRACTITIONER Questions & Answers

  • Question 301:

    DRAG DROP

    PROGRESS

    Stage 3 is nearly finished and the end stage report is being produced.

    Here are three items of information that will be included in the end stage report for stage 3.

    Under which heading (A-F) should they be recorded?

    Choose only ONE heading for each item of information. Each heading can be used once, more than once, or not at all.

    Select and Place:

  • Question 302:

    DRAG DROP

    CONTROLLING A STAGE

    The project is now in stage 2 and work on the 'training venue specifications' work package is underway. This work package includes a phased handover of any completed products to the Training Delivery Manager. The work is running behind

    schedule and over budget.

    Here are three actions that are carried out as part of the 'controlling a stage' process.

    During which activity (A-F) should the action occur?

    Choose only ONE activity for each action. Each activity can be used once, more than once, or not at all.

    Select and Place:

  • Question 303:

    HOTSPOT

    At the end of stage 3, the service provider will be selected and the contract awarded. During stage 4, the Account Manager for the selected service provider will work with the Project Manager to complete the transition of the services to the selected service provider.

    Hot Area:

  • Question 304:

    HOTSPOT

    Column 1 is a list of actions that occur during the Controlling a Stage process. For each action in Column 1, select from Column 2 the PRINCE2 theme that is being applied. Each selection from Column 2 can be used once, more than once or not at all.

    Drop down the answer from column 1 to column 2.

    Hot Area:

  • Question 305:

    HOTSPOT

    Lines 1 to 6 in the table below consist of an assertion statement and a reason statement For each line identify the appropriate option, from options 1 to 6, that applies. Each option can be used once, more than once or not at all.

    Hot Area:

  • Question 306:

    HOTSPOT

    The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project. Column 1 contains a number of risk responses identified by the Project Manager following an assessment of this risk. Column 2 contains a list of threat response types. For each risk response in Column 1, select from Column 2 the type of

    response it represents. Each option from Column 2 can be used once, more than once or not at all. Drop down the right answer.

    Hot Area:

  • Question 307:

    HOTSPOT

    Hot Area:

  • Question 308:

    HOTSPOT The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project. Column 1 contains a number of risk responses identified by the Project Manager following an assessment of this risk. Column 2 contains a list of threat response types. For each risk response in Column 1, select from Column 2 the type of response it represents. Each option from Column 2 can be used once, more than once or not at all. Column 1 contains a number of possible risk responses to the above risk. For each risk response, select from Column 2 the appropriate risk threat response type that it represents. Each selection from Column 2 can be used once, more than once or not at all.

    Hot Area:

  • Question 309:

    The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.

    Using the Project Scenario answer the following question. The Plan for stage 3 has been approved and work has commenced.

    Column 1 contains a number of issues for this project. Select from Column 2 the appropriate category for each issue. Each selection from Column 2 can be used once, more than once or not at all. Drop down the right answer from column 1 to column 2.

    Hot Area:

  • Question 310:

    HOTSPOT

    The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's

    calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.

    There is a major concern over an apparent lack of control of project documentation.

    For each concern listed in Column 1, select from Column 2 the configuration management task that could help address the problem. Each selection from Column 2 can be used once, more than once or not at all.

    Hot Area:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-PRACTITIONER exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.