  • Question 1161:

    Which document defines how a project is executed, monitored and controlled, and closed?

    A. Strategic plan

    B. Project charter

    C. Project management plan

    D. Service level agreement

  • Question 1162:

    Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a typical project progresses?

    A. Risk and uncertainty increase; the cost of changes increases.

    B. Risk and uncertainty increase; the cost of changes decreases.

    C. Risk and uncertainty decrease; the cost of changes increases.

    D. Risk and uncertainty decrease; the cost of changes decreases.

  • Question 1163:

    When alternative dispute resolution (ADR) is necessary, which tool or technique should be utilized?

    A. Interactive communication

    B. Claims administration

    C. Conflict management

    D. Performance reporting

  • Question 1164:

    Which item is an input to the Define Activities process?

    A. Schedule data

    B. Activity list

    C. Risk register

    D. Scope baseline

  • Question 1165:

    What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the earned value (EV) is $50?

    A. 0.50

    B. 0.67

    C. 1.50

    D. 2.00

  • Question 1166:

    A project in which the scope, time, and cost of delivery are determined as early as possible is following a life cycle that is:

    A. Adaptive

    B. Predictive

    C. Incremental

    D. Iterative

  • Question 1167:

    Scope, schedule, and cost parameters are integrated in the:

    A. Performance measurement baseline.

    B. Analysis of project forecasts.

    C. Summary of changes approved in a period.

    D. Analysis of past performance.

  • Question 1168:

    A project manager providing information to the right audience, in the right format, at the right time is an example of which type of communication?

    A. Efficient

    B. Effective

    C. Push

    D. Pull

  • Question 1169:

    A large portion of a projects budget is typically expended on the processes in which Process Group?

    A. Executing

    B. Planning

    C. Monitoring and Controlling

    D. Closing

  • Question 1170:

    Which input provides suppliers with a clear set of goals, requirements, and outcomes?

    A. Procurement statement of work

    B. Purchase order

    C. Source selection criteria

    D. Bidder conference

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.