PMI PMI Certifications CAPM Questions & Answers

  • Question 571:

    Which of the following is a strategy to deal with positive risks or opportunities?

    A. Mitigate

    B. Transfer

    C. Exploit

    D. Avoid

  • Question 572:

    What are the identified risks for doing excessive decomposition in a WBS?

    A. Insufficient project funding and disqualification of sellers

    B. Insufficient project funding and ineffective use of resources

    C. Disqualification of sellers and non-productive management efforts

    D. Non-productive management effort and inefficient use of resources

  • Question 573:

    Which statement is true about the project management body of knowledge?

    A. Recognized by every project manager

    B. Constantly evolving

    C. The sum of all knowledge related to project management

    D. A sum of knowledge that should be applied on every project

  • Question 574:

    The initial development of a Project Scope Management plan uses which technique?

    A. Alternatives identification

    B. Scope decomposition

    C. Expert judgment

    D. Product analysis

  • Question 575:

    Which of the following is a project constraint?

    A. Twenty-five percent staff turnover is expected.

    B. The technology to be used is cutting-edge.

    C. Project leadership may change due to volatile political environment.

    D. The product is needed in 250 days.

  • Question 576:

    An input to the Estimate Activity Resources process is:

    A. Activity resource requirements.

    B. Published estimating data.

    C. Resource calendars.

    D. Resource breakdown structure (RBS).

  • Question 577:

    The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost performance index?

    A. 0.8

    B. 0.89

    C. 1.13

    D. 1.25

  • Question 578:

    Which technique is utilized in the Control Schedule process?

    A. Performance measure

    B. Baseline schedule

    C. Schedule network analysis

    D. Variance analysis

  • Question 579:

    What happens to a stakeholder's project influence over time?

    A. Increases

    B. Decreases

    C. Stays the same

    D. Has no bearing

  • Question 580:

    "Tailoring" is defined as the:

    A. effort of addressing each process to determine which are appropriate and their appropriate degree of rigor.

    B. act of creating a project team with the specialized skills required to produce a required product or service.

    C. action taken to bring a defective or nonconforming component into compliance with requirements or specifications.

    D. adjustment of the respective influences of time, cost, and quality in order to most efficiently achieve scope.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.