  • Question 611:

    A required input for Create WBS is a project:

    A. quality plan.

    B. schedule network.

    C. management document update.

    D. scope statement.

  • Question 612:

    A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?

    A. Three weeks

    B. Four weeks

    C. Five weeks

    D. Six weeks

  • Question 613:

    What is the primary benefit of meeting quality requirements?

    A. Quality metrics

    B. Less rework

    C. Quality control measurements

    D. Benchmarking

  • Question 614:

    What is a tool to improve team performance?

    A. Staffing plan

    B. External feedback

    C. Performance reports

    D. Co-location

  • Question 615:

    Which tool within the Perform Quality Control process identifies whether or not a process has a predictable performance?

    A. Cause and effect diagram

    B. Control charts

    C. Pareto chart

    D. Histogram

  • Question 616:

    During which process would stakeholders provide formal acceptance of the completed project scope?

    A. Perform Quality Control

    B. Verify Scope

    C. Control Scope

    D. Develop Schedule

  • Question 617:

    The PV is $1000, EV is $2000, and AC is $1500. What is CPI?

    A. 1.33

    B. 2

    C. 0.75

    D. 0.5

  • Question 618:

    Types of internal failure costs include:

    A. inspections.

    B. equipment and training.

    C. lost business.

    D. reworking and scrapping.

  • Question 619:

    In a weak matrix, the project managers role is:

    A. part-time

    B. full-time

    C. occasional

    D. unlimited

  • Question 620:

    Which of the following is an example of schedule compression?

    A. Activity sequencing

    B. Resource leveling

    C. Lead and lag adjusting

    D. Crashing

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.