Which of the following is not a planning activity?
A. Environment Planning
B. Capabilities and Opportunities Planning
C. Assumptions and Potentials Planning
D. Standards and Procedures Planning
A common term that is used today for contracting for software development is "performance based contracting." Performance based contracting means:
A. The previous performance of a contractor is a critical success factor
B. The performance criteria for a contractor will be defined in the contract
C. The performance of the software will be defined in the contract
D. The contractor will receive a bonus if performance exceeds the contract provisions
QFD can be used to provide forward and backward traceability of value in the software development life cycle.
A. True
B. False
Which of the following is NOT a major concerns during the operation and maintenance of a purchased application or software?
A. Adequacy of Control
B. Life of Contract
C. Speed of Service
D. Multi-Contractor Problem Resolution
If a software project produced over 100 defects, would you state:
A. The project was poorly implemented
B. The project implemented was acceptable
C. You do not have enough information to state an opinion
D. The project is not under statistical control
Which of the following is not included in 'Failure Cost' under 'Cost of Quality'?
A. Rework Cost
B. Complaints
C. Inspection Cost
D. Damage Claims
Which task or tasks are helpful in building support for quality?
A. Estimate the cost of quality
B. Meet daily on quality
C. Reward quality work
D. All of the above
E. A and C above
Which type of control method does not cause interpersonal problems?
A. Automatic
B. Peer Reviews
C. Supervisory
D. Third Party
E. None of the above
If you had seven programs and the size in 'function points' were 5, 10, 15, 20, 30, 40, and
90. What is the mean size of those seven programs in function points?
A. 20
B. 30
C. 40
D. 50
E. 60
_______________ is a structured, problem-solving technique used to show the relationship between groupings.
A. Brainstorming
B. Matrix
C. Affinity Diagram
D. Pie Chart
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Software exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CSQA exam preparations and Software certification application, do not hesitate to visit our Vcedump.com to find your solutions here.