  • Question 191:

    A customer is reporting that the projects deliverables are not meeting the acceptance criteria. Which of the following documents MOST likely needs to be updated?

    A. Deliverable summary

    B. Quality checklist

    C. Risk register

    D. Resource assignment matrix

  • Question 192:

    During the execution phase of a project, a change request has been approved to add activities to the critical path without altering the schedule. Which of the following techniques will the project manager MOST likely use to deliver the project on time?

    A. Bottom-up estimating

    B. Rolling wave planning

    C. Resource leveling

    D. Fast tracking

  • Question 193:

    Which of the following documents would MOST likely be updated to reflect an approved time change for a regularly scheduled weekly status meeting?

    A. Work Breakdown Structure (WBS)

    B. Responsibility assignment matrix

    C. Communication plan

    D. Change request

  • Question 194:

    Which of the following would MOST likely be reviewed during a project kick-off meeting?

    A. Change requests

    B. Work Breakdown Structure (WBS)

    C. Risk register

    D. Responsibility assignment matrix

  • Question 195:

    Which of the following tools is the BEST to measure data organized in time sequence?

    A. Run chart

    B. Ishikawa diagram

    C. Pareto chart

    D. Histogram

  • Question 196:

    Which of the following tools is the BEST to determine the cause of a problem?

    A. Run chart

    B. Pareto chart

    C. Ishikawa diagram

    D. Histogram

  • Question 197:

    Which of the following is a component of a project charter?

    A. Responsibility assignment matrix

    B. Risk register

    C. Work Breakdown Structure (WBS)

    D. Problem statement

  • Question 198:

    Which of the following is MOST likely to be included in a communication plan?

    A. Change request

    B. Risk register

    C. Frequency

    D. Statement of Work (SOW)

  • Question 199:

    A project team is estimating the amount of time needed to perform an activity. They have recommended an optimistic, pessimistic, and most likely duration to complete the activity. Which of the following would be the BEST tool to estimate the final duration?

    A. PERT

    B. GANTT

    C. GERT

    D. WBS

  • Question 200:

    In order to meet governmental requirement Q555, all materials must meet spec #A-223 qualifications. This is an example of which of the following types of dependencies? (Select Two).

    A. Internal

    B. Discretionary

    C. Fixed

    D. External

    E. Mandatory

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your JK0-017 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.