Which of the following is the purpose of a Pareto diagram?
A. To show the sequence in which work will be performed
B. To create the process that will complete the project
C. To determine the critical path
D. To direct team efforts to the areas that will have the most impact
Refer to the attached Exhibit.
Which of the following is the float of path Start-C-E-Finish in the network diagram?
A. Zero
B. One C. Three
D. Five
A major change has been approved by the change control board and it now needs to be scheduled for implementation. Which of the following is the BEST method of implementing the change?
A. Distribute details of the change per the communication plan, and implement according to the change control process.
B. Ask the change control board to schedule the change, and when scheduled, identify the individual team member responsible for implementing it.
C. Email the project team, identifying the team member responsible for implementing the change, and then schedule it with the appropriate team members.
D. Identify the team member responsible for implementing the change and direct the team member to inform the rest of the project team of the date and time of implementation.
Which of the following shows a project that is presently over its financial budget?
A. CPI = 1.4
B. CPI = 0
C. CV = +$11,000
D. CPI = 0.8
A project manager is reviewing the ownership, date, and the necessary training for a deliverable. Which of the following documents would include this information?
A. Transition plan
B. Quality plan
C. Change Control plan
D. Procurement plan
Several managers are sharing a project team member, which is impacting the progress of both projects. Which of the following BEST describes the situation?
A. Varying work styles
B. Schedule variance
C. Scope creep
D. Competing resource demands
The project manager crashes a project that is behind schedule and under-budget. Which of the following will be the intended result?
A. The project will be behind schedule and over-budget.
B. The project will be on schedule but over-budget.
C. The project will be on schedule and on-budget.
D. The project will be behind schedule and on-budget.
Which of the following is used to display a project schedule?
A. Gantt chart
B. Work Breakdown Structure (WBS)
C. Pareto chart
D. Ishikawa diagram
After final acceptance, which of the following would the project manager use to assess the strengths and weaknesses of the project?
A. Post-project review
B. Transition plan
C. Project kick-off meeting
D. Quality analysis
Refer to the attached Exhibit.
Which of the following is the float of path Start-C-E-Finish in the network diagram?
A. Zero
B. One
C. Three
D. Five
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your JK0-017 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.