CompTIA CompTIA Certifications PK0-003 Questions & Answers

  • Question 111:

    Which of the following are included in phase gate approvals?

    A. Lessons learned, budget schedule review

    B. Change control board, committee consulting

    C. Audit trails, retention, and version control

    D. Cost estimate and resources required

  • Question 112:

    Which of the following is a component of a quality management plan that measures values of the output?

    A. Quality metrics

    B. Quality assurance

    C. Quality control

    D. Quality baseline

  • Question 113:

    Which of the following is included in decision oversight?

    A. Local, state, and federal laws

    B. Change control board, committee consulting

    C. Tollgate approval, project phase transition

    D. Audit trails, retention, and version control

  • Question 114:

    Which of the following are included in operational process compliance?

    A. Audit trails, retention, and version control

    B. Local, state, and federal laws

    C. Tollgate approval, project phase transition

    D. Change control board, committee consulting

  • Question 115:

    Which of the following are included in regulatory compliance?

    A. Change control board, committee consulting

    B. Audit trails, retention, and version control

    C. Local, state, and federal laws

    D. Tollgate approval, project phase transition

  • Question 116:

    Which of the following conflict resolution techniques describes compromising?

    A. Working out an agreement that is acceptable to both sides

    B. One side making the other side do what they are told

    C. Focusing on common interests

    D. Not addressing the conflict

  • Question 117:

    Which of the following conflict resolution techniques describes avoiding?

    A. Reassigning one of the two parties to a different team

    B. Focusing on common interests

    C. Working out an agreement that is acceptable to both sides

    D. Not addressing the conflict

  • Question 118:

    During a conflict, which of the following resolution techniques describes forcing?

    A. Working out an agreement that is acceptable to both sides

    B. Not addressing the conflict

    C. One side making the other side do what they are told

    D. Focusing on common interests

  • Question 119:

    A project is struggling because the sponsor continually has to increase funding which may cause the project to get cancelled. This could have been avoided by using:

    A. Quality metrics.

    B. Change control.

    C. A WBS.

    D. Fixed costs.

  • Question 120:

    A project is having issues because the time required to do the smaller work items in the project were underestimated. This could have been avoided by using:

    A. A WBS

    B. Quality metrics

    C. A scope statement

    D. A budget

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-003 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.