A statement of work (SOW) has been heavily revised by the stakeholders. Which of the following should be implemented to make it easier to determine how many times the document has been revised?
A. Version control
B. A document revision date
C. Approval signatures from each stakeholder
D. A change request
Which of the following is the BEST method to avoid staffing conflict between resource managers and project managers?
A. Allow team members to enter the project as best fits their schedule.
B. Ask the project sponsor for team member assignments.
C. Claim the best department resources before the project starts.
D. Formally request team members early.
Which of the following directly utilize the WBS? (Select TWO).
A. Communication plan
B. Monte Carlo technique
C. Activity estimation
D. Variance analysis
E. Resource assignment
-- Exhibit
-- Exhibit -Click on the exhibit button. Which of the following is the critical path?
A. Start-A-B-E-F-end
B. Start-A-B-C-end
C. Start-A-B-E-C-end
D. Start-A-D-end
-- Exhibit
-- Exhibit -Click on the Exhibit button. Which of the following is the float of the path: start-A-D-end?
A. Zero
B. One
C. Five
D. Nineteen
A conflict has developed among two project team members. The project manager reiterates the areas of agreement and avoids the areas of disagreement. Which of the following BEST describes this conflict resolution technique?
A. Smoothing
B. Compromising
C. Avoiding
D. Negotiating
Which of the following should a project manager do for a team member who does not speak the same language?
A. Hire a translator to assist the team member in communicating.
B. Communicate with the team member using translation software.
C. Send the team member to training on the desired language.
D. Ask for a replacement team member that speaks the same language.
A project manager is completing a project schedule network diagram using boxes to represent the project activities that are connected by lines to show their dependencies. Which of the following tools is the project manager using?
A. AOA
B. WBS
C. ADM
D. PDM
When would a project manager have a closure meeting? (Select THREE).
A. Stage completion
B. Task completion
C. Document completion
D. Project cancellation
E. Project completion
F. Vendor cancellation
Before a change request is presented to the change control board, which of the following should the project manager do?
A. Suggest the board study the cost of the change.
B. Evaluate the affect on all other parts of the project.
C. Review the change request with the project sponsor.
D. Request team member input on the value of the change.
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-003 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.