  • Question 241:

    Which of the following is an acknowledgement that risks may occur, but a response is in place to minimize the risk impact?

    A. Acceptance

    B. Mitigation

    C. Avoidance

    D. Enhancing

  • Question 242:

    A project with a projected budget of $100,000 is 75% complete and has a CPI of .85. Which of the following is TRUE regarding this project?

    A. More project work than projected has been completed

    B. The project is currently in cost overrun

    C. The project EV is 63.75

    D. $85,000 has been spent in the project

  • Question 243:

    Which of the following project plan components would include information regarding the management of issues?

    A. Project Management Plan

    B. Human Resources Plan

    C. Risk Management Plan

    D. Scope Management Plan

  • Question 244:

    Which of the following would be common kick-off meeting activities? (Select TWO).

    A. Develop Work Breakdown Structure

    B. Determine if the project meets organizational goals

    C. Create project charter

    D. Establish project roles and responsibilities

    E. Communicate stakeholder expectations

  • Question 245:

    Which of the following is a common cause of resource conflicts?

    A. Scope creep

    B. Multiple start-to-finish dependencies

    C. No resource baseline

    D. Competing demands

  • Question 246:

    Which of the following conflict resolution techniques involves pushing a single viewpoint at the expense of others?

    A. Smoothing

    B. Forcing

    C. Confronting

    D. Avoiding

  • Question 247:

    An equipment reseller with limited manufacturing capacity is introducing a new product line that requires a custom fabricated part. Which of the following would be the FIRST action that should be taken to obtain the custom part?

    A. Submit an RFI to a local manufacturing facility

    B. Perform a make or buy analysis

    C. Create an RFP to be sent out to current product vendors

    D. Develop detailed drawings and submit to manufacturing for production

  • Question 248:

    Which of the following is a component of a risk management plan?

    A. RAM

    B. RBS

    C. COQ

    D. KPI

  • Question 249:

    Which of the following would be MOST helpful in creating project roles and resource requirements?

    A. Responsibility Assignment Matrix

    B. Project Charter

    C. Work Breakdown Structure

    D. Human Resources Plan

  • Question 250:

    A project manager is mapping out a project based upon the dependencies of the project activities. Which of the following would be BEST for this process? (Select TWO).

    A. CPM

    B. ADM

    C. PDM

    D. Gantt

    E. PERT

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-003 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.