  • Question 171:

    Which of the following would be included in the Project Charter?

    A. Communication activities

    B. Problem statement

    C. Cost baseline

    D. Activity plan

  • Question 172:

    Which of the following does the Critical Path tell the Project Manager? (Select TWO).

    A. Where potential delays in the project might occur

    B. The earliest completion for project work

    C. Activities that can be done in parallel

    D. The allocation time for each person assigned to the project

    E. The longest series of activities

  • Question 173:

    Which of the following conflict resolution techniques results in a lose-lose scenario?

    A. Forcing

    B. Confronting

    C. Compromise

    D. Negotiating

  • Question 174:

    Which of the following types of risk responses would an insurance policy describe?

    A. Acceptance

    B. Transference

    C. Avoidance

    D. Mitigated

  • Question 175:

    The project sponsor has asked for the project to be delivered two months earlier than originally planned with no changes to the deliverables, cost, or the project team. Which of the following schedule planning techniques could be used to meet this request?

    A. Optimizing

    B. Crashing

    C. Delaying

    D. Resource leveling

  • Question 176:

    A common agenda item in a project kick-off meeting should include which of the following?

    A. Communication plan

    B. Roles and responsibilities

    C. Change control process

    D. Dependencies

  • Question 177:

    A project's Critical Path is:

    A. Asequence of activities that takes the shortest time to complete.

    B. Asequence of activities that takes the longest time to complete.

    C. Asequence of the activities that can be delayed without impacting the project's end date.

    D. Asequence of the project's activities required to meet the defined milestones.

  • Question 178:

    An organization with a matrix structure typically:

    A. shares resources between project and functional teams.

    B. has specific levels of authority and supervision.

    C. relies on functional structure to manage projects.

    D. replaces functional structure with project based teams.

  • Question 179:

    The formula for Schedule Performance Index (SPI) is:

    A. SPI = SV/PV

    B. SPI = EV/PV

    C. SPI = EV/SV

    D. SPI = PV/EV

  • Question 180:

    Schedule dependenciesinclude:(Select TWO).

    A. Successor activities

    B. Risks

    C. Constraints

    D. Predecessor activities

    E. Issues

    F. Assumptions

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK1-003 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.