In the planning phase of a project, which of the following activities is performed?
A. Solicitation
B. Perform a feasibility study
C. Appoint a project team
D. Project Charter
As part of the business case, which of the following criteria will drive a feasibility study to be performed?
A. Low complexity project
B. Aligns with the provided RFP
C. There is a legal/regulatory requirement
D. Project has never been done before
Which of the following components of a project charter include identifying important milestones of the project?
A. Key project deliverables
B. High level assumptions
C. Identify stakeholders
D. High level constraints
Which of the following would be used to facilitate communication to investors, customers, and the stakeholders throughout the project?
A. Scope boundaries
B. Status report
C. Work breakdown structure
D. Resource plan
Which of the following steps is required to validate a business case?
A. Feasibility analysis
B. Assign costs
C. Schedule milestones
D. Identify project scope
Which of the following is a characteristic of all projects?
A. Requires PMO approval
B. Cost constraints
C. Limited in number of personnel
D. Temporary in nature
Which of the following is the NEXT step within a project setup after the problem statement has been clearly defined?
A. Identify the project
B. Prepare a project plan
C. Obtain approval
D. Validate the project
Which of the following are benefits of formal project closure? (Select TWO).
A. Ensures the project complies with organizational goals
B. Allows lessons learned to be used in future projects
C. Ensures all pending contracts are closed
D. Assures buy-in from all project stakeholders E. Distributes a new workload and tasks to all project team members
Which of the following is the purpose of a post mortem analysis?
A. Determines the degree of accuracy of activity duration estimates
B. Compares the initial project baselines to end of project baselines
C. Highlights detected quality issues and the resolution to the issues
D. Documents the reasons for an early project closure
Which of the following is a result of an effective communications plan?
A. Required project standards compliance is achieved
B. All project tasks are completed on time
C. Stakeholder expectations are managed
D. A central depository of project materials is created
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK1-003 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.