A company is replacing their file server with a new one. During the data migration, the old file server experiences critical hardware failure. The data migration cannot continue until the hardware is replaced. This repair will put the project behind schedule by a week. Which of the following actions should the project manager do FIRST?
A. Prepare performance report
B. Manage the issue
C. Schedule a meeting
D. Update communication plan
Which of the following regarding project documentation can be found in organizational governance documents? (Select TWO).
A. Length of time project documents must be kept
B. Rules regarding the usage of documentation version numbers
C. Issue management procedures
D. Asset management documentation
E. Team member contact information
A chart of accounts is included in which of the following plans?
A. Quality management
B. Cost management
C. Risk management
D. Procurement management
Which of the following are lose-lose conflict resolution techniques?
A. Negotiating
B. Compromise
C. Confronting
D. Avoiding
The difference between a risk matrix and a risk register is that:
A. the risk register states the risk owner.
B. the risk register contains less information than the risk matrix.
C. the risk matrix states the risk owner.
D. the risk matrix lists the risk description.
A project team is writing a new customized point of sale software. The software needs to calculate sales tax 100% of the time on all taxable items of a receipt. This requirement should be documented in which of the following?
A. Quality control process
B. Quality metrics
C. Quality assurance process
D. Quality check list
A project stakeholder wants to make changes to a project after work on the project has already started. Which of the following should the project manager do FIRST?
A. Assign the request a tracking number and record in change request log
B. Recruit new project team members to expedite the change's completion date
C. Perform an analysis on the requested change submitted by the stakeholder
D. Submit stakeholder's change request to the change control board
Which of the following describes the work package level of a WBS?
A. Project phases
B. Major deliverables
C. The lowest level
D. The project name
Which of the following BEST describes a functional organization?
A. An organization where each employee reports to a Project Manager, who reports to the next level of management. There are no Department Heads.
B. An organization where each employee reports to a Department Head and a Project Manager, splitting their time between department work requirements and projects.
C. An organization where each employee reports to a Department Head, who reports to the next level of management. Departments are managed independently, and Project Managers are staff who report to the Department Heads.
D. An organization where each employee reports to a Department Head, who reports to the next level of management. Departments manage projects independently.
Which of the following is included in the project charter?
A. Work assignments
B. Problem statement
C. Cost-benefit analysis
D. Feasibility assessments
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK1-003 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.