A. Measure of product backlog items (PBI) remaining
B. Measure of quality of features delivered in an iteration
C. Measure or required effort to complete an iteration
D. Measure of the effectiveness of the retrospective meeting
The purpose of a Sprint retrospective is for the Scrum team to:
A. Review stories planned for the next sprint and provide estimates,
B. Demonstrate completed user stories to the Product Owner.
C. Determine what to stop doing, start doing, and continue doing.
D. Individually provide status updates on user stories in progress.
What Agile concept expresses delivering value in slices rather than in layers/stages?
A. Definition of Done
B. Value Mapping
C. Sashimi
D. Lean Value
Which of the following is NOT a principle from the Agile Manifesto?
A. Our highest priority is to satisfy the customer through early and continuous delivery of valuable software.
B. Business people and developers must work together daily throughout the project.
C. Continuous creation of technical debt and good design enhances agility.
D. Working software is the primary measure of progress.
In the Kano Model of customer satisfaction, this type of feature makes a product unique from its competitors and contributes 100% to positive customer satisfaction:
A. Excitement
B. Performance
C. Must-have
D. Threshold
Which chart shows the total number of story points completed through the end of each iteration?
A. Iteration Burndown chart
B. Cumulative story point Burndown chart
C. Daily Burndown chart
D. Burnup chart
What Agile planning artifact should be updated at minimum semi-annually?
A. Product Vision
B. Product Roadmap
C. Release Plan
D. Sprint Plan
E. Daily Plan
What Agile planning artifact is updated minimally once a year by the Product Owner?
A. Product Vision
B. Product Roadmap
C. Release Plan
D. Sprint Plan
E. Daily Plan
DSDM uses MoSCoW technique to create the prioritized requirements list. In MoSCoW technique, `M' stands for:
A. Most useful
B. Must have
C. Must not have
D. Minimum marketable feature
What Agile planning artifact is created by the Product Owner and the development team?
A. Product Vision
B. Product Roadmap
C. Release Plan
D. Sprint Plan
E. Daily Plan
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-ACP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.