Which of the following is an Agile practice promoted by XP that is often used on conjunction with other Agile methods?
A. Dynamic Systems Development Method (DSDM)
B. Feature Driven Development (FDD)
C. Adaptive Software Development (ASD)
D. Test Driven Development (TDD)
Alistair Cockburn created the Crystal Family of Agile Methods, all of whose names contain colors of quartz crystals taken from geology. What two characteristics of an Agile project are used to determine the color of the Crystal method?
A. Size and complexity
B. Duration and complexity
C. Size and criticality
D. Duration and criticality
Which of the following is NOT recognized as a "unit" that can be used for estimating the size of the requirements on your Agile project?
A. Real time
B. Relative size
C. Ideal time
D. Ideal size
One of the major tools and techniques used in Lean Software Development is Value Stream Mapping. What is the primary purpose of value stream mapping?
A. To improve business processes
B. To identify and eliminate waste
C. To ensure product quality
D. To increase customer value
When implementing Agile Project Management, risk management that occurs simply by following Agile best practices such as iterative planning and review activities is called:
A. Inherent risk management
B. Organic risk management
C. Overt risk management
D. Intrinsic risk management
Extreme Programming (XP) defines four basic activities that are performed during the software development process. These include designing, coding, testing and ...?
A. Collaborating
B. Leveling
C. Communicating
D. Listening
Agile project management and product development use several types of documents specific to each iteration; they are known as "artifacts". All of the following documents are Agile iteration artifacts except:
A. Iteration Vision Statement
B. Iteration Backlog
C. Iteration Plan
D. Iteration Burndown Chart
In Sprint Planning, the development team estimates User Stories provided by the Product Owner and agrees to ones that can be completed in the Sprint. This is an example of:
A. Osmotic Communication
B. Reciprocal Commitment
C. Universal Acceptance
D. Tacit Agreement
On XP teams, what is expected from the Project Manager?
A. Coach the team on Agile practices
B. Help the team work with the rest of the organization
C. Provide domain expertise to the team
D. Define the software
Which of the following is NOT an Extreme Programming Practice?
A. Pair Programming
B. Planning Game
C. Test Driven Development
D. Extreme Persona
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-ACP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.