Suppose the current release will be complete after 6 two-week iterations. A team member is insisting that the Product Owner write the acceptance test cases for the entire release. How should the Scrum Master respond?
A. Since the release duration is not very long, agree with the idea and explain the advantage of doing this to Product Owner
B. It's up to the team and Product Owner to determine if it is a good idea.
C. Explain that stories should only be discussed in detail prior to development. Elaborating stories not in the next couple of iterations is wasteful.
D. Decide to dedicate first Sprint to elaborating all the stories
Suppose your team is working to create a commercial website and is in the process of developing User Stories by role. One team member suggests rather than only thinking about the target user, we should also think of some exceptional users who use the system very differently. What type of user is this team member referring to?
A. High Risk User
B. Admin Role
C. Extreme Persona
D. Performance Tester
An iteration takes place in a time frame with specific start and end dates, called a time-box. Which of the following is NOT an advantage of time-boxing?
A. Establishes a WIP limit
B. Forces prioritization
C. Demonstrates progress
D. Helps control technical debt
A change made to the internal structure of software that makes it easier to understand and cheaper to modify but does not change its observable behavior is referred to as:
A. A Spike
B. Technical debt
C. A User Story
D. Refactoring
Which of the following are 2 attributes of Exploratory testing? (Choose two.)
A. It involves minimum planning and maximum test execution
B. It is typically automated
C. It is unscripted testing
D. It is often the sole testing technique
Which of the following testing is done manually by the XP team?
A. Regression testing
B. Unit testing
C. Integration testing
D. Exploratory testing
Identify the three components of the Agile Triangle. (Choose three.)
A. Quality
B. Value
C. Cost
D. Constraints
E. Scope
F. Leadership
What is the name of this facilitated process? One or more team members sequence the product backlog from smallest to largest User Story. The rest of the team validates the sequence. The whole team uses a sizing method such as T-shirt size or Fibonacci sequence to group the user stories.
A. Relative estimation
B. Pairwise comparison
C. Planning Poker
D. Affinity estimating
The 3 items are required for an Agile, adaptive environment: (Choose three.)
A. People
B. Process
C. Product
D. Tools
E. Technology
There are four critical actions that should be embraced by an adaptive leader: improving speed-to-value, having a passion for quality, doing less, and ________________.
A. Inspiring staff
B. Managing conflict
C. Facilitating meetings
D. Ensuring effective communication
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-ACP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.