Exam Details

  • Exam Code
    :PMI-RMP
  • Exam Name
    :PMI Risk Management Professional (PMI-RMP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :580 Q&As
  • Last Updated
    :Apr 12, 2025

PMI PMI Certifications PMI-RMP Questions & Answers

  • Question 451:

    An organization with a large computer network identified a potential cyber security threat. Although certain measures were implemented to avoid the risk, the cyber security threat occurs. The measures were partially successful and a new unforeseen risk emerges.

    What should the risk owner do?

    A. Develop an efficient network protection solution quickly to mitigate the risk.

    B. Escalate the case to the risk manager and wait for their instructions.

    C. Conduct an analysis to determine the root cause of the failed response.

    D. Apply a work around to eliminate or mitigate the impact of the threat.

  • Question 452:

    A risk manager is confident that they have identified and quantified the risks and opportunities for a project. When presenting their work to management, on what areas should the risk manager focus? (Choose two.)

    A. Risks that are tied to the success of the organization

    B. Risks as they apply to the organization's overall risk management philosophy and strategic ambition

    C. Huge opportunities that possibly bring an additional 30% return for 10 projects in the next year

    D. Risks related to cost that will impact the major projects that are currently in the execution phase

    E. Risk mitigation actions that will require work from stakeholders

  • Question 453:

    An organization faces immense competition in the market and decides to accelerate a key project. What is the first action for the project risk manager to take?

    A. Update the risk register

    B. Meet with the project's stakeholders

    C. Revise the risk management plan

    D. Ensure sufficient resources are available

  • Question 454:

    During project planning, a risk is identified for which the risk manager has defined a mitigation strategy. Later during project execution, this risk still leaves substantial residual risk.

    What should the risk manager do to handle this situation?

    A. Revisit this risk in the risk register and redefine the mitigation strategy.

    B. Activate the contingency plan to handle this risk during execution.

    C. Mark this new risk as an extremely high priority and inform all stakeholders.

    D. Ask the project sponsor for more budget to deal with this risk.

  • Question 455:

    A risk manager of a complex project has identified a risk and believes a deeper understanding of the source and likelihood is necessary. How should the risk manager proceed?

    A. Develop and employ an Ishikawa diagram

    B. Analyze the assumptions and constraints

    C. Perform a review of project documents

    D. Create prompt lists for expert interviews

  • Question 456:

    The risk manager of a major project needs to ensure the organizational process assets (OPAsj are updated as a result of risk management activities. How will the risk manager accomplish this?

    A. Ensuring that the project sponsor is kept well-informed

    B. Arranging periodic risk: management process audits

    C. Communicating the status of risks regularly to stakeholders

    D. Monitoring costs with intervention when necessary

  • Question 457:

    A new risk manager has been hired on a project and meets with the project director. The project director supplies the project's risk register and asks the risk manager for an analysis of its effectiveness.

    What two actions should the risk manager do next? (Choose two.)

    A. Check to ensure that the risk is supported by a Monte Carlo simulation.

    B. Check to ensure that the risks are gathered using Delphi technique.

    C. Check for risk classification and that probability and impact are identified.

    D. Check to ensure that risk origin, triggering event, and ownership is identified.

    E. Check to ensure the risk meeting agenda and supporting documents are distributed.

  • Question 458:

    After a number of risk workshops, risks have been identified. Which is the first element the risk owner should look for in the response plan to help mitigate the risks?

    A. Probability of a response triggering a secondary risk

    B. How the response will affect the quality of the components

    C. If the risk response is tied to an activity on the critical path

    D. Verify due dates for the actions have been identified

  • Question 459:

    A risk manager for a cross-functional project is initiating the risk identification process. The risk manager conducted some meetings for stakeholders to express their concerns, but some stakeholders are complaining that their opinions were not considered.

    How should the risk manager address these concerns?

    A. Refer to the requirements documentation to confirm stakeholder requirements as they relate to risks.

    B. Refer to the project charter to find guidelines and stakeholder communication channels.

    C. Review the stakeholder register and stakeholder engagement plan to communicate and solicit stakeholder input.

    D. Rewrite the risk register to include the additional possible risks and inform the stakeholders.

  • Question 460:

    A risk management professional is in the process of categorizing risks when a subject matter expert (SME) suggests categorizing the risks by their impact to the project objectives. Why should the risk management professional use this approach?

    A. To enable the team in identifying the specific causes of risks associated with project objectives.

    B. To ensure that project priorities are being appropriately factored into risk response plans.

    C. To determine there more attentive project leadership and organizational involvement is needed.

    D. To assign risks and risk severities to functional discipline and departments effectively.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-RMP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.