Exam Details

  • Exam Code
    :PMI-RMP
  • Exam Name
    :PMI Risk Management Professional (PMI-RMP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :580 Q&As
  • Last Updated
    :Mar 26, 2025

PMI PMI Certifications PMI-RMP Questions & Answers

  • Question 571:

    A project manager is educating the project team on risk management regarding the role of threats and opportunities. The team decides to log the opportunities in the current project's risk register to try to maximize their chances of occurrence.

    What should the project team do next?

    A. Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis.

    B. Log the threats in the risk register to try to minimize the probability of occurrence.

    C. Log the threats in the risk register to try to maximize the probability of occurrence.

    D. Update the project management plan to ensure the results of the opportunities are captured.

  • Question 572:

    A project manager is working on a complex construction project. During the risk identification process, hundreds of risks were identified. The team seems to be confused regarding on which risks to focus. The project manager advises the team to go ahead and start assessing the likelihood and impact of each risk.

    What process is this part of?

    A. Plan Risk Management

    B. Perform Qualitative Risk Analysis

    C. Perform Quantitative Risk Analysis

    D. Monitor and Control Risk

  • Question 573:

    A risk management professional is currently facilitating the risk planning process with the project team. To increase the breadth of considered risks, the team wants to include high- level and strategic project risks.

    What should the risk management professional do next?

    A. Perform a sensitivity analysis to the higher-level aggregate activities

    B. Develop a risk breakdown structure (RBS) identifying the potential risk categories

    C. Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis

    D. Perform a base line Monte Carlo simulation to address overall threats to project objectives

  • Question 574:

    A project manager was informed that the testing of the latest component in the project's software update release was not successful. As a result, 1he delivery timelines for the software release wifi be delayed, The project manager did not previously capture this as a risk to the project.

    What should the project manager do next to avoid similar risks?

    A. Add contingencies to other tasks to mitigate similar risks.

    B. Reassess risks with a new assumptions and constraints analysis.

    C. Review the risk response plan looking for lessons learned.

    D. Log the event in the issue log and update the project management plan.

  • Question 575:

    A project manager has finished the project charter for a project and has now moved into the planning phase. In the first planning meeting, the project manager is trying to determine the risk tolerance and risk attitudes of the project's key stakeholders.

    What is the first resource the project manager should reference?

    A. Benefits management plan

    B. Enterprise environmental factors (EEFs)

    C. Project charter

    D. Requirements management plan

  • Question 576:

    A subcontractor working on a project may cause delays in the construction schedule. The project manager records this risk in the risk register and issues a change request sponsor rejects the change request.

    What should the project manager have done differently?

    A. Executed the risk strategy response and recorded it in the risk register.

    B. Performed an analysis to affirm the request is valid before submitting.

    C. Informed the client and the project sponsor that the request is being submitted.

    D. Contacted the other stakeholders so they know the request is in process.

  • Question 577:

    A project has a significant impact on an organization. Multiple stakeholders expressed concerns regarding the overall project risk during construction of the risk management plan, and they agreed that the risk appetite is low. What should the project risk manager monitor closely?

    A. Risk thresholds

    B. Risk response strategies

    C. Risk management reports

    D. Risk breakdown structure (RBS)

  • Question 578:

    A project manager has determined that they cannot outsource work nor eliminate the scope. They also discover that they cannot buy insurance or mitigate the risk.

    What should the project manager do?

    A. Avoid the risk

    B. Transfer the risk

    C. Ignore the risk

    D. Accept the risk

  • Question 579:

    A list of risks was identified that could occur during the design phase. Now, the team finished the design phase and those risks did not materialize.

    What should the project manager do next?

    A. Close the risks and update their status in the risk register.

    B. Use their contingency with other risks that are still open.

    C. Remove the risk from the list as they are no longer applicable.

    D. Reevaluate those risks' severity, and update the risk register.

  • Question 580:

    A risk manager manages risks in a construction project. A stakeholder mentions that if there is less than a 50% chance of rain, construction should continue. Another stakeholder says that if there is less than a 60% chance of rain, construction should continue.

    What should the risk manager do next to find out the correct limit?

    A. Review the agreed-upon risk tolerance

    B. Perform a sensitivity analysis of the risk

    C. Find out the stakeholders' risk appetite

    D. Use industry standard risk thresholds

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-RMP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.