Exam Details

  • Exam Code
    :PMI-RMP
  • Exam Name
    :PMI Risk Management Professional (PMI-RMP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :580 Q&As
  • Last Updated
    :Mar 26, 2025

PMI PMI Certifications PMI-RMP Questions & Answers

  • Question 561:

    The project manager asks the risk manager to determine the initial risk assessment for a six month initiative that is about to kick-off. Which two artifacts will help the risk manager conduct the related analysis? (Choose two.)

    A. Work breakdown structure (WandS)

    B. Project organizational chart

    C. Configuration management plan

    D. Brainstorming

    E. Monte Carlo analysis

  • Question 562:

    A new risk manager has been assigned to a delayed strategic project. The risk manager presented a new plan to get the project back on track using lessons learned and applying risk response strategies. Senior management wants to remove contingency reserves because they want to finish the project earlier.

    What should the risk manager do in this scenario?

    A. Review project schedule estimates.

    B. Change the response strategies.

    C. Reduce the contingency reserves.

    D. Conduct a risk planning workshop.

  • Question 563:

    A project manager identified a risk of communication issues with the client which may impact the project schedule. A member of (he sales team advises that this client prefers face-to- face conversations.

    What should the project manager do to avoid this risk?

    A. Record this risk and the clients preference in the risk register.

    B. Ask the sales person to lead the communication with the client

    C. Call the client and advise that online communication is easier and faster.

    D. Meet the client and plan tor critical milestone meetings.

  • Question 564:

    The project manager wants to use an objective method to evaluate the key project risks and develop response plans.

    What action should the risk manager propose?

    A. Ask the team to perform an earned value analysis.

    B. Review the lessons learned from other projects.

    C. Ask the team to prepare a Monte Carlo analysis.

    D. Ask the risk expert to perform a PESTLE evaluation.

  • Question 565:

    During the design phase the project team is exploring various architecture options. After reviewing the results of design pilot, two conflicting infrastructure pieces were identified.

    What action should the project manager take?

    A. Reassess the design for the two pieces.

    B. Escalate the situation and request approval to move forward.

    C. Confirm the results through a second pilot.

    D. Update the assumptions log and assess the risk associated with it.

  • Question 566:

    When approving the risk contingency budget for a project, the CEO notices each team has a different approach to report risks and their impacts. The CEO decides to create a new centralized risk management function to help resolve the problem.

    How does centralizing the risk management function help resolve the problem?

    A. Enhance the process of identification of different Individual project risks.

    B. Allows monitoring the impact against the overall project risk exposure.

    C. Establishes risk sources and ownership for trigger monitoring.

    D. Creates a single repository for all project risk documents.

  • Question 567:

    Upon reviewing the risk analysis results, the project manager notices several risks that occur more frequently than others. What should the project manager do?

    A. Reduce the probabilities of those risks on the risk register

    B. Transfer ownership of those risks to the customer

    C. Implement the risk handling strategies for those risks

    D. Request additional management reserve for those risks

  • Question 568:

    A risk manager completed risk response planning for a project that is currently in the execution phase. During a periodic review of the risk register, the project manager recognizes that some key secondary risks have not been considered.

    Who should the project manager hold accountable for missing the risks?

    A. The audit team

    B. The risk manager

    C. The risk owners

    D. The discipline engineers

  • Question 569:

    As per the risk analysis process carried out for a project, two risks are registered. The probability risk A will occur is 40% and its monetary impact to the project is US$100,000. The probability risk B will occur is 60% and its monetary impact to the project is US$20,000.

    What is the total contingency budget that should be created?

    A. US$68,000

    B. US$52,000

    C. US$120,000

    D. US$80,000

  • Question 570:

    Stakeholder deliverable reviews will start soon and additional work is expected to resolve any issues or required adjustments. Budget overruns during execution have put serious constraints on the remainder of the project's budget.

    What should the project manager do next?

    A. Request a budget relief using the management reserve.

    B. Conduct a risk reassessment and reserve analysis.

    C. Review the consequences of potential changes.

    D. Coach stakeholders on risk identification practices.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-RMP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.