Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional (PMI-SP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :Mar 29, 2025

PMI PMI Certifications PMI-SP Questions & Answers

  • Question 101:

    Joe is the project manager of the HJN Project. Joe's project is a renovation of an office building. There must be 30 hours between the painting activity and the carpet activity in the project schedule to eliminate the risk of wet paint getting on the carpet. What is the best approach Joe can do to alleviate this issue?

    A. Add lead time to the painting activity.

    B. Change the relationship of the carpet activity and the painting activity to finish-to-finish.

    C. Create a dummy activity between the painting activity and the carpet activity for the duration of the drying process.

    D. Add lag time to the carpet activity.

  • Question 102:

    You are the project manager of the NHL Project for your organization. You are working with your project team to create the schedule baseline for this project. According to you, which of the following statements describes how the schedule baseline is created?

    A. It is derived from the constraints of the project.

    B. It is assigned to the project by management.

    C. It is created by the stakeholders.

    D. It is developed from the schedule network analysis.

  • Question 103:

    In which of the following process groups does Integration Change Control Process fall?

    A. Execution

    B. Initiating

    C. Planning

    D. Monitoring and Controlling

  • Question 104:

    Virginia is the project manager for her company. She has used a previous project as a basis for her current project because they are similar in nature. Virginia has adapted nearly all of the previous project plans for her current project including the project schedule, risk register, and communications management plan. She has worked with management to update the plans to adapt them to the current project. What are the previous project management plans called in this instance?

    A. Expert judgment

    B. Analogous estimate

    C. Templates

    D. Parametric estimate

  • Question 105:

    You are the project manager for your organization. Your project will be utilizing a piece of equipment during its process of completion. There is some concern that your project's use of the equipment may conflict with another project. What document will help you determine when and how long you will use the shared equipment?

    A. Project schedule

    B. Project scope

    C. Project calendar

    D. Resource calendar

  • Question 106:

    What schedule analysis simulation tool allows you, the project manager, to review possible combinations of events such as optimistic, most likely and pessimistic outcomes for your project?

    A. PERT

    B. Monte Carlo

    C. PMIS

    D. GERT

  • Question 107:

    You work as the project manager for Blue Well Inc. You are working with your project team to schedule the days the project work will take place. You have created a project network diagram as shown in the figure:

    Based on this diagram, find out the earliest day on which Activity G can be started.

    A. Day 13

    B. Day 7

    C. Day 22

    D. Day 17

  • Question 108:

    Sam is the project manager for his organization. His project is not doing well on project schedule performance, and management wants him to predict how the project schedule and cost will end. Management has asked Sam to report and forecast his project's performance based on the Delphi Method, scenario building, technology forecasting, and to forecast by analogy. What forecasting method is management asking Sam to use?

    A. Judgmental methods

    B. Time series methods

    C. Causal/econometric methods

    D. Earned value management method

  • Question 109:

    You are the project manager for your organization. You are discussing an upcoming project with management and they would like you to begin decomposing the project work packages into activities as soon as possible. You have explained to the management that you would like to involve your roject team before the decomposition of the work packages begins. Why would you want your project team to involve in this activity?

    A. To understand the exact type of work the project team will be completing

    B. To help the activity go faster

    C. To get better and more accurate results through the decomposition

    D. To create assignments for the project team as the activities are discussed

  • Question 110:

    You are the project manager for your organization. You are working with your virtual team to create activity duration estimates for your current project. This virtual team is comprised of team members from around the world. Much of this process will be completed by geographical locations though some conferences will require all the team members to participate and to coordinate the activities that will interact between the different sites. The project manager must consider all of the following when creating the activity duration estimates except for which one?

    A. Project calendar

    B. Critical path

    C. Resource calendar

    D. Time zone differences

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.