Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional (PMI-SP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :Mar 29, 2025

PMI PMI Certifications PMI-SP Questions & Answers

  • Question 91:

    Paula works as a project manager for her organization. She is working with the project team to define the activity attributes. Which of the following is NOT a valid activity attribute?

    A. Activity Name

    B. Activity ID

    C. Risk event

    D. WBS ID

  • Question 92:

    You are project manager of HHK project. Examine the network diagram given below:

    A vendor reports that he will be four days late on the materials you'll need in order to complete Activity

    A. Based on the project network diagram, how many days can Activity E be delayed?

    B. Four days

    C. Six days

    D. Five days

    E. Zero, it is on the critical path.

  • Question 93:

    In which of the following group decision making techniques does the largest block in a group decide the group decision even if a bulk is not achieved?

    A. Majority

    B. Unanimity

    C. Dictatorship

    D. Plurality

  • Question 94:

    There are seven inputs to the estimate activity durations process. Which one of the following is NOT an input to this process?

    A. Scope baseline

    B. Activity attributes

    C. Activity list

    D. Activity resource requirements

  • Question 95:

    Your project team has identified a project risk that must be responded to. The risk has been recorded in the risk register and the project team has been discussing potential risk responses for the risk event. The event is not likely to happen for several months but the probability of the event is high. Which one of the following is a valid response to the identified risk event?

    A. Risk audit

    B. Technical performance measurement

    C. Earned value management

    D. Corrective action

  • Question 96:

    What component of the change management system is responsible for evaluating, testing, and documenting changes created to the project scope?

    A. Scope Verification

    B. Configuration Management System

    C. Project Management Information System

    D. Integrated Change Control

  • Question 97:

    All of the following statements about the critical path are false except for which one?

    A. The critical path cannot be crashed.

    B. The critical path is the shortest path in the project network diagram.

    C. The critical path is always one path with the longest duration.

    D. The critical path shows the project's earliest date for completion.

  • Question 98:

    You work as a project manager for BlueWell Inc. Which of the following tools/techniques will you use to demonstrate how a process behaves over time, and when a process is subject to special cause variation, resulting in an out-of-control condition?

    A. Pareto Chart

    B. Ishikawa Diagram

    C. Scatter Chart

    D. Control Chart

  • Question 99:

    Ned is the project manager for his organization. Ned is using a standard tool to capture, store, and distribute information to the stakeholders about the project costs, schedule, and performance. What term is assigned to this communication tool?

    A. Project management information system

    B. Table reporting

    C. Reporting system

    D. Communications management system

  • Question 100:

    You have created the project network diagram for your project. Management is reviewing the network diagram and they are curious as to why you have included levels of effort activities as start-to-start and finish-to-finish successor activities for work that uses particular manufacturing equipment. You explained that the levels of effort activities are maintained for the equipment. This relationship and scheduling scenario is also known as what term?

    A. Project management overhead

    B. Hammock activity

    C. Subproject

    D. Finish-to-Start

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.