Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional (PMI-SP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :Apr 07, 2025

PMI PMI Certifications PMI-SP Questions & Answers

  • Question 141:

    Don is the project manager of the NQP project for his organization. This project is scheduled to last for 18 months and will have several elements of the project that have government regulations. Management is concerned with the regulations and would like Don to report on the activities that will be affected by the regulations. Which of the following documents should Don refer to, for the information on the activities and the regulations?

    A. Risk management plan

    B. Activity list

    C. Activity list and attributes

    D. Risk register

  • Question 142:

    Which of the following processes fall under the Project Integration Management knowledge area? Each correct answer represents a complete solution. Choose all that apply.

    A. Quality Assurance

    B. Project Plan Development

    C. Integrated Change Control

    D. Project Plan Execution

  • Question 143:

    Ned is the project manager of the HYQ Project. In Ned's project, the management has requested that he enforce resource leveling so that the maximum amount of hours in the project per worker will not exceed 25 hours per week. Ned's pay is based on how quickly he can complete the project work. What must Ned do to accommodate the change in the resource allotment if he has to finish the project on time?

    A. Crash the project.

    B. Add more risk mitigation.

    C. Reduce the amount of labor.

    D. Reduce the project scope.

  • Question 144:

    Joseph works as the project manager of the NHQ Project. He has created the project network diagram as shown in the figure: Based on the network diagram, find out which path is the critical path for this project?

    A. ABEHJ

    B. ABDIJ

    C. ABDHJ

    D. ACFIJ

  • Question 145:

    You work as a project manager for BlueWell Inc. You have to identify the specific actions to be performed to produce the project deliverables. For this, you have to explain the three inputs for the define activities process to your project team. Which of the following is NOT a valid input?

    A. Work Breakdown Structure

    B. Enterprise Environmental Factors

    C. Scope baseline

    D. Organizational Process Assets

  • Question 146:

    You work as a project manager for BlueWell Inc. Which of the following techniques will you use to determine whether particular work can best be accomplished by the project team or must be purchased from the outside sources?

    A. Contract Types

    B. Expert Judgment

    C. Procurement Negotiations

    D. Make-or-Buy Analysis

  • Question 147:

    You are the project manager of a project that has a budget of $875,000 and you have completed 40 percent of the project work. Due to some errors, however, you have actually spent $425,000 of the budget. Management wants to know what the project's cost performance index is. What value do you report?

    A. -$75,000

    B. $350,000

    C. .82

    D. -$187,500

  • Question 148:

    Frank is the project manager of a construction project. In this project, Frank has elected to allow the interior design phase of the project to overlap with the pool construction phase of the project. Normally, Frank would not allow these two phases to overlap, but for this project, he has elected to do so in order to compress the project schedule. What is this schedule compression technique called?

    A. Resource leveling heuristic

    B. Lead time

    C. Fast tracking

    D. Crashing

  • Question 149:

    Tom works as the project manager for BlueWell Inc. He spends the majority of his time communicating with team members and the project stakeholders. Various communication skills are involved in the communication processes. Which communication skills are involved in this process? Each correct answer represents a part of the solution. Choose all that apply.

    A. Internal and External

    B. Vertical and Horizontal

    C. Confronting and problem solving

    D. Formal and Informal

  • Question 150:

    Tom is the project manager for the ABC Construction Company. As part of the project scheduling for the construction of a new office building, he has allotted time for the inspectors of the building structure, as well as electrical, plumbing, and safety into the project's schedule. These inspectors can be considered what type of dependency in the project?

    A. Mandatory dependencies

    B. Required dependencies

    C. Discretionary dependencies

    D. External dependencies

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.