Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional (PMI-SP)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :Apr 07, 2025

PMI PMI Certifications PMI-SP Questions & Answers

  • Question 161:

    John is the project manager for his organization. Management has asked John to fast track his project in order to reach a particular date for the project completion. When John fast tracks the project what project management component must be updated to reflect this decision? Choose the best answer.

    A. Organizational process assets

    B. Cost management plan

    C. Resource calendars

    D. Risk register

  • Question 162:

    Donna is the project manager of the QSD Project and she believes Risk Event D in the following figure is likely to happen.

    If this event does happen, how much will Donna have left in the risk contingency reserve if none of the other risk events have happened?

    A. $35,000

    B. $41,700

    C. $6,700

    D. $14,000

  • Question 163:

    Harry works as a project manager for BlueWell Inc. A risk that has been identified and analyzed in the project planning processes is now coming into fruition. Who among the following is responsible for implementing the risk responses or contingency plan?

    A. Risk owner

    B. Harry

    C. Project sponsor

    D. Subject matter expert

  • Question 164:

    Amy works as a project manager for BlueWell Inc. She is working on the SDI project, which has a BAC of $2,816,000. She is currently 20 percent complete with this project, though she should be 25 percent complete with the project work. The project has consumed $495,000 of the project budget to date. Management has asked her the project's Estimate To Complete (ETC) based on the current project performance. What is the ETC for this project?

    A. $1,312,504

    B. $1,979,952

    C. $1,541,544

    D. $2,474,952

  • Question 165:

    You work as a Project Manager for Tech Perfect Inc. You are looking for performance efficiencies of a project. The related key values are provided in the table below:

    What will be the cost variance (CV) of the project at the current point of time?

    A. +80

    B. -80

    C. -10

    D. +10

  • Question 166:

    Terri is the project manager for her organization and she is working with her project team to develop the project schedule. She has identified the float in her project although some of the activities where float exists may be susceptible to risk in the project execution. She is also concerned that the critical path may change during the project if the risk events come into execution. What scheduling method is Terri using in this example?

    A. Critical chain method

    B. Risk analysis method

    C. Activity on the arrow method

    D. Critical path method

  • Question 167:

    What project management plan will document the time frame and frequency for the distribution of required information?

    A. Scope Management Plan

    B. Communications Management Plan

    C. Stakeholder Management Plan

    D. Schedule Management Plan

  • Question 168:

    You are the project manager for the GRT Project in your organization. You have created your time duration estimates based on historical information, but the estimates are not holding true in your current project. Unfortunately, many activities are late. You have decided to create a PERT estimate with your project team for each of their activities. What is the formula used for PERT?

    A. O+M+P

    B. (O+M+P)/3

    C. (O+4M+P)/6

    D. Average of the estimates

  • Question 169:

    You are the project manager of the NHQ project. Your project has a budget of $1,258,456 and is scheduled to last for three years. Your project is currently forty percent complete though it should be forty- five percent complete. In order to reach this point of the project, you have spent $525,000. Management needs a performance report regarding the NHQ project. What is the planned value for this project?

    A. $566,305

    B. $1,258,456

    C. -$54,044

    D. $503, 382

  • Question 170:

    You work as the project manager for BlueWell Inc. You are recording the activity status for your project team's performance in the project. Based on the current performance your project is likely to be three months late. What type of communication should be generated based on this performance issue?

    A. Issue report

    B. Exceptions report

    C. Variance analysis

    D. Performance report

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.