Which of the following is an activity in a typical configuration management process?
A. Evaluation.
B. Identification.
C. Registration.
D. Justification.
Which of the following defines the term 'deployment baseline'?
A. The starting point for creating a resource histogram.
B. The basis for creating an organisational breakdown structure.
C. The starting point for the monitoring of project risks.
D. The basis for progress monitoring.
Which of the following statements about scheduling is false?
A. Defines the sequence of activities.
B. Considers work calendars and time contingency.
C. Provides a baseline for safety considerations.
D. Quantifies the required resources.
The definition of benefits management includes which key activities?
A. Planning, analysis and integration of project benefits.
B. Justification, validation and acceptance of project benefits.
C. Identification, tracking and realisation of project benefits.
D. Realisation, acceptance and integration of project benefits
Product breakdown structures illustrate the required scope of work by a hierarchical structure itemising the:
A. components of each product.
B. budget of each product.
C. benefits of each product.
D. risks of each product.
The main aim of quality management is to:
A. prepare a high-quality management plan.
B. ensure that deliverables meet appropriate standards.
C. validate the use of consistent standards.
D. determine whether to accept change requests.
Which of the following is a purpose of issue management?
A. To stop issues occurring within the project.
B. To address and resolve the issues that occur.
C. To address and resolve uncertainty.
D. To reschedule activities to reduce costs
Which technique could be used by a project manager when resources are limited?
A. Resource aggregation.
B. Resource estimation.
C. Resource levelling.
D. Resource expansion
One advantage of virtual communications is:
A. that nonverbal signals can have an impact on discussions.
B. it's easy to detect signs of conflict within the project team.
C. access to a wider resource pool for the project.
D. that the project team will always be co-located.
Which of the following is the purpose of an estimating funnel?
A. Keeping resource usage to a minimum to help reduce costs.
B. Supporting the production of comparative estimates.
C. Identifying where costs can be minimised when preparing a budget.
D. Representing increasing levels of estimating accuracy achieved through the life cycle
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only APM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-PFQ exam preparations and APM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.