The purpose of project progress reporting is to:
A. ensure a simpler critical path.
B. enable the tracking of project deliverables.
C. ensure stakeholder acceptance of project deliverables.
D. provide an increased total float.
Which of the following actions would not help a team leader influence the performance of their team?
A. Creating an exclusive environment.
B. Providing clear roles and responsibilities.
C. Promoting openness and honesty.
D. Developing a trusting relationship.
One difference between a project and business as usual is:
A. projects achieve specified benefits but business as usual has only vague benefits.
B. projects drive change whereas business as usual continues existing activities.
C. projects have tightly controlled budgets whereas business as usual does not.
D. projects have unclear deadlines but business as usual has multiple milestones
Portfolio management includes prioritising:
A. projects and/or programmes that contribute directly to the organisation's strategic objectives.
B. projects with exceptionally high returns on investment.
C. projects and programmes over business as usual.
D. projects which maximise change over those which maximise investment
To develop and establish a proper communication plan within a project, the project manager needs to consider which type of analysis?
A. Budget.
B. Stakeholder.
C. Resource.
D. Schedule
Which of the following is a responsibility of the project sponsor?
A. Creating a project cost breakdown structure.
B. Authoring the project management plan.
C. Creating a project work breakdown structure.
D. Owning the project business case.
Which of the following is the responsibility of a project manager?
A. Ensuring a project is aligned to the organisation's strategy.
B. Focusing on project benefits and aligning priorities.
C. Achieving the project's success criteria.
D. Improving process, tools and techniques used in a project
A project manager might use a PESTLE analysis in order to:
A. mitigate all possible risks to the project.
B. identify and mitigate factors that may affect the project.
C. control technological change during the project.
D. consider team social roles in early stages of the project
Which of the following are phases in an iterative project life cycle? 1) Concept 2) Feasibility 3) Deployment 4) Development
A. 3 and 4 only
B. 1, 2 and 3
C. 1 and 2 only
D. 2, 3 and 4
The purpose of quality assurance is to:
A. provide confidence the project will satisfy the relevant quality standards.
B. determine a set of procedures and standards for project management.
C. inspect, measure and test deliverables and processes.
D. define the scope and specifics of a project's deliverables
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only APM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-PFQ exam preparations and APM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.