In your plant, MRP is activated.
Which option do you have to exclude a materila from the MRP run? (Choose 2)
A. Use specific MRP controller
B. Use a specific material group
C. Use a specific material status
D. Use a specific MRP type
Which mhetods are available for goods issue posting of material components for process orders? (Choose 2)
A. Transfer order
B. Picking list
C. Blackflushing
D. Kanban
When can the automatic material availability check occur in a production order? (Choose 2)
A. At order release
B. At order confirmation
C. At order creation
D. At order settlement
During production order creation, several valid production versions are found. How does the system choose the production version?
A. Planned order or material number
B. Valid period or sale order
C. Alphanumeric or quota arrangement
D. Lot size or material cost
You want to triggering-house production of a semi-finished mater al before a sales order for the corresponding finished good is received.
Which planning strategy supports the consumption of planned independent requirements for the semi-finished material?
A. Make-to-order production (20)
B. Planning at assembly level (70)
C. Planning with final assembly (40)
D. Planning without final assembly (50)
Which of the following is valid sequence of the main activities in production order processing? (Choose 2)
A. Creation, availability check, release, material widrawal, confirmation
B. Creation, release, printing, goods issue, confirmation, goods receipt
C. Creation, printing, release, goods issue, confirmation, goods receipt
D. Creation, release, settlement, goods issue, confirmation, goods receipt
In the Capacity Scheduling Table, which settings can you select for the planning strategy? (Choose 3)
A. Planning mode
B. Finiteness level
C. Fixed pegging
D. Direction E. Scheduling control
The MRP run detected a shortage of a materila that you sorce from an external supplier in full pallets. How can you make sure you will only recive full pallets?
A. Use the fixed lot procedure.
B. Use the MRP type for vendor managed inventory.
C. Use the minimum order quantity
D. Use the reorder point
You use planning strategy Finite Scheduling - with Reverse adn want to allow scheduling in the past. How can you achive this?
A. Specify a negative offset time in the strategy profile.
B. Specify a positive planning horizon in the strategy profile.
C. Specify a negative lanning horizon in the strategy profile.
D. Specify a positive offset time in the strategy profile.
What is the difference between co-products and by-products?
A. Only co-products appear in the process or production order settlement rule.
B. Only co-products can be manufactured in isolation from the main product.
C. Only co-products are identified by a special item category in the bill of material (BOM).
D. Only by-products have a zero inventory valuation.
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_TS422_2021 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.