What are the consequences when you assgn a planned order to a production line manually, using the planning table in repetitive manufacturing?
A. The planed order's component availability is checked.
B. The planed order is converted to production order.
C. The planned order's components are copied to the picking list.
D. The planed order generates capacity requirements
How can SAP S/4HANA support a GMP-compliant production process? (Choose 3)
A. Approved resources
B. GMP-compliant flag
C. Recipe approval
D. Batch record
E. Digital signature
Which information is required when you created a production master in SAP S/4HANA? (Choose 2)
A. Selective screen for views
B. Product type
C. Base unit of measure
D. Industry sector
You need to model goods receipt processing time in detailed scheduling. Whic modeling options do you have? (Choose 2)
A. Model a transportation resorce in the location master.
B. Model a seperate resource in the production data structure.
C. Model a resource inbound in the location master.
D. Model a handling resource in the location master and goods receipt time in the material master.
Which of the following questions do you have to answer before you start creating a BOM? (Choose 2)
A. In which storage location is the BOM required?
B. Which Valid To information is necessary?
C. Is the material type allowed in the BOM?
D. What status does the BOM have?
Which alternative item strategies are available in bills of materials (BOM) in SAP S/4HANA? (Choose 2)
A. First in first out (FIFO)
B. 100% check
C. Simultaneous
D. By usage probability
Which SAP solutions support the supplier area in the portfolio of the Digital Value Network? (Choose 3)
A. SAP Ariba
B. SAP Hybris
C. SAP Concur
D. SAP Fieldglass
E. SAP SuccessFactors
Mode selection is one of the scheduling options available in Advanced Planning in SAP S/4HANA. When can you use mode selection?
A. When multiple operations are maintained for one product
B. When alternate resources are used within one operation
C. When multiple planned orders exist on one resource
D. When multiple production versions are maintained for one product
What could be the reason for multiple commitment of invidula capacities, where several operations have the same scheduled dates on a work center (or resource) after planing? (Choose 2)
A. The work center has several invidula capacities.
B. The finite Scheduling indicator is NOT set in the strategy profile.
C. The Change Planning Direction indicator is set in strategy profile.
D. Alternative work centers are fully occupied.
Which time elements are relevant for lead time scheduling of a production order? (Choose 2)
A. Float after production
B. Planned delivery time
C. Total replenishment lead time
D. Setup time
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only SAP exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your C_TS422_2021 exam preparations and SAP certification application, do not hesitate to visit our Vcedump.com to find your solutions here.