How does agile address the risk associated with the project not being fully understood at the beginning?
A. By allowing a lot of detail at the start
B. By avoiding too much detail at the start
C. By requiring details at the start
D. By preventing the analysis of details at the start
Which is typically used in agile when estimating detailed requirements during sprint planning?
A. Rationalism
B. Trading
C. Visioning
D. T-shirt sizing
Which is an advantage of using the PRINCE2 Agile behavior `collaboration'?
A. It ensures that there are no surprises
B. It allows people to provide cover for one another
C. It uses experimentation to expand requirements
D. It uses learning to help improve products
What is an epic?
A. A low-level requirement
B. A fine-grained user story
C. A detailed feature
D. A high-level requirement
Which is a purpose of the quality theme?
A. To define the specific conditions that enable a product to be usable
B. To determine how the means of delivering products is communicated
C. To evaluate whether the project continues to be achievable
D. To assess any potential improvements to a product
Which statement about the `embrace change' target is CORRECT?
A. It minimizes the time needed to train a new team member
B. It reduces the planning of dependencies between projects
C. It reduces testing in order to meet deadlines
D. It encourages the customer to raise new ideas
Which two statements are key responsibilities of supplier representative?
1.
They highlight areas that the project may impact from a technical perspective.
2.
They are partially assigned to the delivery team.
3.
They create the project's specialist products.
4.
They prioritize requirements.
A. 1 and 2
B. 2 and 3
C. 3 and 4
D. 1 and 4
What should be decided when configuring PRINCE2 effectively?
A. What to remove and where to add guidance
B. Where to put the emphasis and where to add guidance
C. What to significantly change to create the right blend
D. Which areas are not enabled to work with agile
When tracking progress, which term describes using agile techniques at the delivery level, and traditional techniques at the direction and management levels?
A. Preferable
B. Typical
C. Effective
Why are team working agreement produced?
A. To create structure so that the team manager can assess individual performance
B. To evolve the effectiveness and behaviors of the self-organizing team by agreeing values
C. To make the team rules visible to the project manager for monitoring purposes
D. To ensure that the delivery team members comply with company policy
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-AGILE-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.