Which is a typical characteristic of `business as usual' work?
A. It requires a specific dedicated project manager
B. It is executed by program management
C. It is delivered by a temporary team
D. It is delivered by an established team
Which is a purpose of the `controlling stage' process?
A. To execute and deliver the project product
B. To establish whether the project is complete
C. To report stage progress to the project board
D. To draft the plan for the next stage's work
Which statement about velocity is CORRECT?
A. It is based on the concept of rationalism
B. It is shown by the ideal line on a bum-down chart
C. It describes how much work is getting done
D. It tracks the time and cost of a timebox
Which statement about the `accept that the customer doesn't need everything' target is correct?
A. It gives confidence on the progress of the project
B. It can result in the early delivery of a minimum viable product
C. It allows misunderstandings to be dealt with appropriately
D. It is achieved by managing the culture of the team carefully
What needs to happen when new detailed requirements are added to a timebox?
A. Requirements of a similar level of effort should be removed
B. More people should be added to the delivery team
C. The delivery milestones should be reviewed and re-planned
D. Formal change control should be applied
Which statement about the `keep teams stable' target is CORRECT?
A. It applies primarily to the long term, such as a project or a program
B. It is the primary reason why the tolerance for cost is set to zero
C. It prevents compromising the overall quality level of the product
D. It results in the early delivery of a minimum viable product
What should the business case state about the minimum viable product (MVP)?
A. When the MVP will be defined
B. That the MVP must go into operational use
C. What the MVP is
D. That the MVP is the same as project viability
How does the change theme regard change in PRINCE2 Agile?
A. As disruptive
B. As something to be avoided
C. As a necessity
D. As inevitable
Which two statements about tailoring the business case in an agile environment are CORRECT?
1.
It should be unnecessary because products of the highest value will be delivered first.
2.
It should identify the minimum viable product and when it will be delivered.
3.
It should take into account that the scope may be reduced during the course of the project.
4.
It should show the features, the order in which they will be delivered and any dependencies.
A. 1 and 2
B. 2 and 3
C. 3 and 4
D. 1 and 4
What term is used to describe boards that display what work needs to be completed for people working on a project?
A. Work in progress limit
B. Information radiator
C. Highlight report
D. Glad! Sad! Mad!
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-AGILE-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.