  • Question 21:

    In Scrum, what answers the question `what can be done this sprint?'

    A. Daily scrum

    B. Sprint review

    C. Sprint planning

    D. Increment

  • Question 22:

    Which statement explains the setting of the cost tolerance for a project in an agile context?

    A. Cost tolerance is flexed

    B. Cost tolerance can be fixed or flexed

    C. Cost tolerance can be fixed and flexed

    D. Cost tolerance is fixed

  • Question 23:

    Which role is responsible for facilitating the Agilometer assessment?

    A. Project board

    B. Project manager

    C. Team manager

    D. Customer subject matter expert

  • Question 24:

    What is an epic?

    A. A detailed user story with high business value

    B. The set of products handed over to the users

    C. A high-level user story that is quite broad or vague

    D. A prioritized list of requirements to be delivered in a sprint

  • Question 25:

    Which is NOT one of the core concepts of Lean Startup that apply to PRINCE2?

    A. To use empiricism, based on knowledge that comes from experience

    B. To build, measure, learn from your experiences

    C. To create a minimum viable product to manage uncertainty

    D. To fail fast, if you are going to fail

  • Question 26:

    What information is NOT typically displayed on a burn chart?

    A. Effort remaining

    B. Definition of `ready'

    C. Actual amount of work done

    D. Amount of time elapsed

  • Question 27:

    In which area is Agile strongest when blending with PRINCE2?

    A. Product delivery

    B. Project management

    C. Project direction

    D. Product management

  • Question 28:

    Which statement describes the Kanban approach?

    A. It is used to make system improvements using visualization and by controlling work in progress

    B. It is an iterative timeboxed approach that helps teams generate value

    C. It was originally focused in creating new companies and is now used to speed up product delivery

    D. It has defined processes, products and roles used to iteratively deliver outputs using timeboxing

  • Question 29:

    Which statement about the `protect the level of quality' target is CORRECT?

    A. It is achieved by allowing enough time for testing

    B. It is achieved by using the same team members

    C. It gives confidence on the progress of the project

    D. It delivers the early realization of benefits

  • Question 30:

    Which statement explains the target `be on time and hit deadlines' for flexible delivery?

    A. It reduces testing in order to meet deadlines

    B. It sets the project baseline at the correct level

    C. It enables team dynamics to remain the same

    D. It improves the supplier's reputation with the customer

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-AGILE-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.