Exam Details

  • Exam Code
    :PRINCE2-FOUNDATION
  • Exam Name
    :PRINCE2 Foundation
  • Certification
    :PRINCE2 Certifications
  • Vendor
    :PRINCE2
  • Total Questions
    :1158 Q&As
  • Last Updated
    :Mar 27, 2025

PRINCE2 PRINCE2 Certifications PRINCE2-FOUNDATION Questions & Answers

  • Question 1131:

    Identify the missing word(s) in the following sentence... PRINCE2 recommends three [ ? ] to reflect the needs of the different levels of management involved in a project.

    A. Levels of issue

    B. Stakeholders

    C. Levels of plan

    D. Types of risk responses

  • Question 1132:

    Which of the following is NOT one of the three levels of plan recommended by PRINCE2?

    A. Stage

    B. Team

    C. Benefits Review

    D. Project

  • Question 1133:

    The period of time for which it is possible to accurately plan in detail is known as?

    A. The predicting period

    B. The planning horizon

    C. The stable schedule

    D. The panorama plan

  • Question 1134:

    Which of the following shows the scope of a plan?

    A. The full content of a product checklist

    B. The related product breakdown structure

    C. The composition of a Project Product Description

    D. All of the project's Configuration Item Records

  • Question 1135:

    Which product does the Project Board use as a base against which to monitor project progress on a stage by stage basis?

    A. Stage Plan

    B. Project Plan

    C. Programme Plan

    D. Benefits Review Plan

  • Question 1136:

    According to PRINCE2, it is seldom desirable, or possible, to plan an entire project in detail at the start. Which one of the following is given as a reason for this?

    A. It can be difficult to predict the actual performance of resources

    B. All aspects of planning become more difficult the further into the future they extend

    C. Sufficient detail is only known once the relevant stage has begun

    D. The supplier is unlikely to comprehend the detailed schedule

  • Question 1137:

    Why does PRINCE2 recommend having three levels of plan?

    A. The more levels there are, the more stable the plan detail will become

    B. Aspects of planning become more difficult the further into the future they extend

    C. To reflect that there are 3 key stakeholder project interests

    D. To reflect the needs of the different levels of management involved in the project, stage and team

  • Question 1138:

    Which of the following Plans can be approved by the Project Manager?

    A. Project Plan

    B. Team Plan

    C. Exception Plan at stage-level

    D. Stage Plan

  • Question 1139:

    In which process is it decided that an Exception Plan should be created to replace a Stage Plan?

    A. Directing a Project

    B. Controlling a Stage

    C. Managing a Stage Boundary

    D. Closing a Project

  • Question 1140:

    Which product identifies the source products from which a product is to be derived?

    A. Product Breakdown Structure

    B. Product checklist

    C. Product Description

    D. Project approach

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.