Which takes place within the Managing a Stage Boundary process?
A. Periodic review of progress against the Stage Plan
B. Obtain approvals for all completed products
C. Escalation of Issue Reports created during the current stage
D. Review of the business justification for the project
Which is a type of issue?
A. Problem/concern
B. Follow-on action recommendation
C. Exception Report
D. Identified threat
Which is a purpose of the Directing a Project process?
A. Enable the Project Board to exercise overall control of a project
B. Prepare a solid foundation for the project
C. Establish the prerequisites for the initiation of a project
D. Assign Work Packages
Which is a purpose of a Risk Management Strategy?
A. Communicate how risk management will be implemented throughout the wider corporate organization
B. Capture and maintain information on all identified risks relating to the project
C. Document specific actions for responding to risks
D. Describe the procedures and techniques for managing project risks
Which is NOT a purpose of the Plans theme?
A. Facilitate communication
B. Establish the project's structure of accountability
C. Define the means of delivering the products
D. Ensure targets are achievable
Which is a purpose of a Project Brief?
A. Define how and when a measurement of the achievement of the project's benefits can be made
B. Define any lessons from previous projects and how they may affect this project
C. Communicate the quality techniques and standards to be applied to achieve the required quality levels
D. Provide sufficient information for the decision on whether to initiate the project
Which is a purpose of the Organization theme?
A. Define the total resource requirements of the project
B. Capture the project acceptance criteria
C. Define the responsibilities for managing teams
D. Establish mechanisms to judge whether the project is desirable and achievable
When authorizing a stage, in which product would the Project Board look for an explanation of any deviations from the approved plans that are within tolerance?
A. Lessons Report
B. End Stage Report
C. Benefits Review Plan
D. Project Initiation Documentation
Which of the following are a purpose of the Benefits Review Plan?
1.
Define how a measurement of the achievement of the project's benefits can be made
2.
Define what benefits assessments need to be undertaken
3.
Define the project, in order to form the basis for its management and an assessment of its overall success
4.
Define the activities required to measure the expected project's benefits
A. 1, 2, 3
B. 1, 2, 4
C. 1, 3, 4
D. 2, 3, 4
Identify the missing word in the following sentence. PRINCE2 recommends three levels of [ ? ] to reflect the needs of the different levels of management involved in a project.
A. Product
B. Activity
C. Plan
D. Benefit
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.