In what plan should project closure activities be planned?
A. Closure Stage Plan
B. Stage Plan for the final management stage
C. Initiation Stage Plan
D. Team Plan
What is a purpose of a Configuration Management Strategy?
A. Define the various types of quality methods to be applied to the project's products
B. Provide details of the current state and version of each configuration item
C. Record how the products will be protected and uniquely identified
D. Define what the budget will be for controlling any risks
Which product would define a product's quality tolerance?
A. Quality Register
B. Product Description
C. Stage Plan
D. Quality Management Strategy
Identify the missing words in the following sentence... A purpose of the Quality theme is to [ ? ]
A. Provide a systematic approach which ensures that issues possibly affecting the project's quality performance target are managed appropriately
B. Ensure any threats to the quality targets are identified, assessed and controlled
C. Provide all personnel involved in the project with information regarding whether the targets of time, cost and quality are achievable
D. Ensure the project's products meet business expectations
Which integrated element is described as being the guiding obligations and good practices which determine whether the project is genuinely using PRINCE2?
A. Principles
B. Processes
C. Themes
D. Tailoring PRINCE2 to the project environment
Which product would be at the centre of any impact assessment of risks, issues and changes?
A. Highlight Report
B. Business Case
C. Lessons Log
D. Communication Management Strategy
Which of the following risk responses can be used to seize an opportunity to ensure a risk will occur?
A. Accept
B. Exploit
C. Enhance
D. Transfer
Which of the following steps looks at the aggregated net effect of a project's treats and opportunities?
A. Plan
B. Assess (estimate)
C. Examine
D. Assess (evaluate)
Identify the missing words in the following sentence... A PRINCE2 project focuses on [ ? ], in particular their quality requirements
A. The definition and realization of benefits<
B. The definition and delivery of products
C. Project management team roles and responsibilities
D. The outcomes expected from the using the outputs
How does PRINCE2 define a project?
A. A temporary team that is created to direct and oversee a collection of related projects in order to deliver outcomes and benefits related to the organization's strategic objectives
B. A temporary organization that is created for the purpose of delivering one or more business products according to an agreed Business Case
C. A permanent organization that is created for the purpose of realizing one or more business benefits
D. A permanent team that is created to deliver a series of business change initiatives
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.