Which is a purpose of a Configuration Item Record?
A. Record quality issues found in a quality test of the product
B. Explain which procedure should be used for updating the Configuration Item Records of products completed in the stage
C. Explain which procedure should be used for transferring completed products into the operational and maintenance environment
D. Record the development status of a product in a completed Work Package
What role agrees the techniques, products and constraints for a Work Package with the Project Manager?
A. Executive
B. Project Assurance
C. Senior Supplier
D. Team Manager
Identify the missing words in the following sentence. If the Project Manager needs to know the results of a quality review, the [ ? ] will provide a summary together with the date of any follow- up meeting.
A. Stage Plan
B. Issue Register
C. Daily Log
D. Quality Register
How is the Project Initiation Documentation used during the Closing a Project process?
A. As the basis for comparing the original aim of the project against what was actually achieved
B. Provides the controls for the final stage of the project
C. Updated to include relevant lessons from previous projects
D. Provides the Project Product Description for approval by the Project Board
The incorporation of the primary stakeholders on the project management team supports what principle?
A. Continued business justification
B. Defined roles and responsibilities
C. Manage by stages
D. Learn from experience
Which describes risk appetite?
A. An organization's attitude towards risk-taking
B. Probable effect on the project delivering its objectives
C. Probable timeframe within which a risk may occur
D. Level of risk exposure that, when exceeded, triggers an exception
Which is a purpose of the Business Case theme?
A. Establish mechanisms to monitor and compare actual achievements against those planned
B. Establish methods to judge whether the ongoing project is justified
C. Assess and control uncertain events or situations
D. Describe how, when and at what cost products can be delivered
What role is responsible for creating a Team Plan in the Managing Product Delivery process?
A. Project Manager
B. Team Manager
C. Project Support
D. Senior User
Which is one of the six aspects of project performance that needs to be managed?
A. Customers
B. People
C. Benefits
D. Processes
What is the trigger for the Starting up a Project process?
A. Project Brief
B. Project Plan
C. Project mandate
D. Outline Business Case
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.