Which is assumed to be a customer's responsibility in the PRINCE2 customer/supplier environment?
A. Specify the desired result
B. Provide the resources and skills to deliver the desired result
C. Ensure the technical integrity of aproject
D. Develop a project's products
Which does NOT reflect the PRINCE2 principle of continued business justification?
A. There must be a justifiable reason for starting a project
B. The business justification drives decision making
C. If a project is no longer forecast to deliver a financial benefit, it should be stopped.
D. If a project can no longer be justified, it should be stopped
From whom does a Team Manager obtain approval for a completed product?
A. Project Manager
B. Project Support
C. The authoritydefined in the Product Description
D. Senior Supplier
Identify the missing word(s) in the following sentence. The Quality theme provides a set of rules and procedures which ensure that the [ ? ] created meet(s) the needs of the business.
A. controls
B. products
C. project management team
D. stages
Who should act as the communication channel between a project and corporate or programme management?
A. Project Board
B. Project Assurance
C. Project Manager
D. Project Support
Which is NOT considered when defining risk tolerance?
A. A Project Board's attitude towards risk taking
B. The allocated risk budget
C. An organization's risk appetite
D. The amount of risk a Project Board considers acceptable
Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?
A. Those with a financial interest in the project
B. Those who will manage the project on a day-to-day basis
C. Those who will specify the desired outputs of the project
D. Those who will create the project's outputs
Identify the missing words in the following sentence. A purpose of the Plans theme is to [ ? ] the project's plans
A. define a coding system to provide a unique identifier for the products within
B. summarize the results of the quality activities performed on
C. provide a framework to design, develop and maintain
D. define the project benefits to be achieved by each of
Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?
A. Create a separate Project Board to manage the supplier elements of the project
B. Create multiple smaller Project Boards during the process of Starting up a Project, one for each of the project's stages.
C. Create user and supplier groups
D. Appoint corporate quality assurance to perform the Project Assurance role for all members of the Project Board
Which is part of quality control?
A. Undertake quality reviews
B. Write Product Descriptions
C. Provide assurance that the project is being conducted properly
D. Document the customer's quality expectations
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.