  • Question 311:

    Identify the missing word in the following sentence. The guiding obligations and good practices which determine whether the project is genuinely being managed using PRINCE2 form the [ ? ] of the method.

    A. Principles

    B. Themes

    C. Processes

    D. Techniques

  • Question 312:

    Which of the following statements about customer's quality expectations and acceptance criteria are true?

    1.

    Customer's quality expectations form a specific and precise list of measurable criteria that a project product should meet in order to be acceptable to key stakeholders.

    2.

    Acceptance criteria are often expressed in broad terms as a means to gain common understanding of general quality requirements.

    A. Only 1 is true

    B. Only 2 is true

    C. Both 1 and 2 are true

    D. Neither 1 or 2 are true

  • Question 313:

    Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?

    A. Project Brief

    B. Project Initiation Documentation

    C. Project mandate

    D. Benefits Review Plan

  • Question 314:

    Which is a typical core activity within configuration management?

    A. Quality assurance

    B. Risk management

    C. Verification and audit

    D. Progress reporting

  • Question 315:

    Which is NOT a purpose of the Initiating a Project process?

    A. Enable a Project Boarddecision about the commitment of resources to a project

    B. Enable an organization to understand the work that needs to be done to deliver a project's products before a project is approved

    C. Establish solid foundations for a project

    D. Enable the Project Board to decide whether it is worthwhile to initiate a project

  • Question 316:

    Which is a typical core activity within configuration management?

    A. Issue management

    B. Quality inspection

    C. Quality inspection

    D. Preparation

  • Question 317:

    How many roles make up the Project Board?

    A. One

    B. Two

    C. Three

    D. Four

  • Question 318:

    Which process is triggered towards the end of the final stage when all the assigned work has been completed?

    A. Managing a Stage Boundary

    B. Managing Product Delivery

    C. Closing a Project

    D. Controlling a Stage

  • Question 319:

    Which aspect of project performance must be managed to ensure the project's products are fit for purpose?

    A. Benefits

    B. Quality

    C. Risk

    D. Scope

  • Question 320:

    Which should be provided by corporate or programme management before the Starting up a Project process commences?

    A. A Project Brief

    B. Sufficient information to identify the prospective Executive

    C. The Project Initiation Documentation

    D. Authority to initiate a project

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.