Identify the missing word in the following sentence. The risk response type [ ? ] can be used to respond to a threat and an opportunity
A. Avoid
B. Reduce
C. Share
D. Transfer
Which role is responsible for creating Checkpoint Reports?
A. Senior Supplier
B. Team Manager
C. Change Authority
D. Project Support
Which is an objective of the Directing a Project process?
A. Create and authorize the project mandate
B. Providemanagement control and direction
C. Control the day-to-day running of the project
D. Provide accurate progress information to the Project Manager
Which is NOT one of the PRINCE2 integrated elements?
A. Tailoring PRINCE2 to the project environment
B. The processes
C. The products
D. The themes
Which is a purpose of the Starting up a Project process?
A. Provide information so a decision can be made asto whether a project is viable and worthwhile to initiate
B. Define the means of communication between the project and corporate or programme management
C. Define the project controls
D. Record any identified risks in the Risk Register
How many management stages should a PRINCE2 project consist of?
A. Start up stage, initiation stage and at least one other management stage to cover the remainder of the project
B. Start up stage, at least one other management stage to cover the remainder of the project and a closing stage
C. Initiation stage and at least one other management stage to cover the remainder of the project
D. Start up stage, initiation stage and a closing stage
Which is a recommended quality review team role?
A. Project Manager
B. Assurance
C. Project Support
D. Administrator
Which statement about the quality review technique is FALSE?
A. It enables a check to be made on a product's fitness for purpose
B. It defines the quality responsibilities of the project team
C. It supports the management of future changes by providing abaseline for a product
D. It is used to gain wider acceptance of a product by involving key interested parties
Which is an objective of the Closing a Project process?
A. Prepare the plan for the next stage
B. Assess any benefits that have already been realized
C. Produce a Benefits Review Plan to identify what benefits are expected
D. Check that all benefits are realized before closing a project
Which step in the issue and change control procedure considers alternative options for responding to an issue that is being managed formally?
A. Capture
B. Examine
C. Propose D. Decide
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.