Identify the missing product in the following sentence.
When assessing an issue during the Controlling a Stage process, the [ ? ] provides essential information to evaluate the viability of the project.
A. Project Brief
B. Benefits Review Plan
C. Project Initiation Documentation
D. Configuration Management Strategy
Which role does NOT set tolerances?
A. Corporate or programme management
B. Project Board
C. Change Authority
D. Project Manager
Which aspect of project performance must be managed to avoid misunderstandings on what the project is to deliver?
A. Timescale
B. Scope
C. Risk
D. Costs
Which product describes the roles and responsibilities for achieving the effective management of anticipated threats and opportunities in a project?
A. Quality Management Strategy
B. Risk Management Strategy
C. Communication Management Strategy
D. Configuration Management Strategy
During the Initiating a Project process, which product is updated to incorporate the estimated time and costs from the Project Plan?
A. Project Product Description
B. Business Case
C. Project Brief
D. Project mandate
What theme provides all management levels within the project management team with mechanisms for monitoring and control?
A. Progress
B. Change
C. Organization
D. Quality
Which does a Project Manager produce to define and control the work to be done?
A. Configuration Item Record
B. Stage scope tolerance
C. Team Plan
D. Work Package
Which is a purpose of the Organization theme?
A. Ensure that the project organization structure will enable the project to deliver the business benefits in the required time frame
B. Define accountability within the project
C. Identify risk owners for the project
D. Define the quality methods and responsibilities for the management of the project
Identify the missing word(s) in the following sentence.
Following initiation, the Controlling a Stage process is used to manage and control each [ ? ] of a project.
A. technical stage
B. benefit
C. management stage
D. Team Plan
Identify the missing words in the following sentence.
A benefit of adopting PRINCE2 is that it can be applied to [ ? ] - and can easily be implemented alongside specialist techniques.
A. any type of project
B. programmes and projects
C. all types of programmes
D. business as usual
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.