Which is NOT a purpose of a Benefits Review Plan?
A. Define the periodover which the cost-benefit analysis will be based
B. Describe how to measure the performance of the project's products in operational use
C. Define the scope, timing and ownership of the benefit reviews required D. Describe how to measure and confirm anybenefits that are to be realised after the project is closed
Who carries out audits that are independent of the project?
A. Quality assurance
B. Project Assurance
C. Project Support
D. Project Manager
Which statement is true for ALL project stakeholders?
A. Internal to the corporate organization
B. May either affect or be affected by the project
C. Review the Communication Management Strategy
D. Support the project
Which theme defines the accountability for realization of the project's benefits?
A. Plans
B. Progress
C. Organization
D. Quality
Which is NOT a PRINCE2 principle?
A. Learn from experience
B. Customer/supplier environment
C. Defined roles and responsibilities
D. Continued business justification
Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?
A. Off-specifications
B. Follow-on action recommendations
C. Issue Register
D. Risk Register
What product defines the reporting requirements between the Project Manager and Team Manager?
A. Project Brief
B. Product Description
C. Team Plan
D. Work Package
What product identifies the management stages and other major control points in a project?
A. Business Case
B. Project Plan
C. Work Package
D. Project Brief
Which is NOT a requirement of a Stage Plan?
A. Produced to an appropriate level of detail to enable day-to-day control
B. Produced near to the end of the previous management stage
C. Approved and signed-off by Project Assurance
D. Approved at the end of a management stage
When considering how long the project stages should be, which might be a reason for one stage to be longer than others?
A. A substantial amount of the project budget is to be spent
B. More human resources are required than in other stages
C. The risk is lower
D. No changes to the project management team are envisaged
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.