What is the minimum number of management stages required by PRINCE2?
A. Two stages: to initiate and to deliver the project
B. One stage: to cover the whole project
C. Three stages: to initiate, to deliver and to close the project
D. Four stages: to start, to initiate, to deliver and to close the project
Which statement about applying the 'tailor to suit the project' principle is CORRECT?
A. PRINCE2 can be tailored to be used with any type of project
B. A technically complex project should NOT tailor PRINCE2
C. The tailoring of PRINCE2 is MOST appropriate for agile projects
D. A project which is part of a programme should NOT tailor PRINCE2
What should be recorded in a quality register?
1.
Activities to ensure the products are fit for purpose
2.
Identified threats and opportunities
3.
Problems and concerns to be managed informally
4.
Roles responsible for reviewing the project's products
A. 1 and 2
B. 2 and 3
C. 3 and 4
D. 1 and 4
Which is a minimum requirement for applying the organization theme?
A. The project's approach to engaging with its stakeholders must be defined
B. Roles must be combined to reduce the number of individuals needed on the project
C. During a procurement the senior supplier must be appointed from the customer organization
D. The project team must change at each end stage of the project life cycle
In which process is the work to be done assigned to a team manager?
A. Directing a project
B. Managing a stage boundary
C. Controlling a stage
D. Managing product delivery
Which is a responsibility of the project board?
A. To manage the team managers and project support
B. To ensure production of the project's outputs
C. To ensure effective communication with external stakeholders
D. To implement the change control approach
What is a goal of the 'implement' step within the recommended risk management procedure?
A. To prepare specific management responses to identified risks
B. To monitor the effectiveness of actioned risk responses
C. To estimate the risk to the project in terms of probability and impact
D. To communicate information related to the risks faced by the project
Identify the missing words in the following sentence. Project assurance personnel [ ? ] the project manager.
A. are able to overturn the decisions of
B. must be accountable to
C. should support
D. report to the project board and
Which principle helps to ensure that all changes to the outputs are agreed?
A. Defined roles and responsibilities
B. Focus on products
C. Learn from experience
D. Manage by exception
Identify the missing word in the following sentence.
[ ? ] is the measurable decline resulting from a negative outcome.
A. An exception
B. A dis-benefit
C. An off-specification
D. A risk
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.