Controlling a Stage process views the project from which role's perspective?
A. Team Manager
B. Project Board
C. Project Assurance
D. Project Manager
Which process would have a purpose of taking action to ensure the stage remains within tolerance?
A. Directing a Project
B. Controlling a Stage
C. Managing a Stage Boundary
D. Managing Product Delivery
The Controlling a Stage process is used for which of the following?
A. Day-to-day management of each management stage of a project
B. Closure of the project prematurely or at the project's natural end
C. Creation and quality control of the specialist products
D. Preparing a Stage Plan near the end of each stage
Which of the following is a specific objective of the Controlling a Stage process?
A. Attention is focused on delivery of the stage's products
B. Assure the Project Board that all products in the Stage Plan for the current stage have been completed and approved
C. Work on products allocated to the team is authorized and agreed
D. The various ways the project can be delivered are evaluated and a project approach selected
In which process would a concern about the amount of stage tolerance remaining be recorded in the Issue Register?
A. Directing a Project
B. Managing a Stage Boundary
C. Managing Product Delivery
D. Controlling a Stage
In which situation might the Controlling a Stage process be used?
A. Managing a long initiation stage of a complex project
B. Managing the activities of a complex programme
C. Managing support activities following the handover of the products to the operational environment
D. Creating an Exception Plan to replace the current Stage Plan
If a Project Manager were to receive progress information on a Work Package during a stage, which one of the following products would the Project Manager update to show the progress that's been made?
A. Checkpoint Report
B. Stage Plan
C. Benefits Review Plan
D. Project Plan
Identify the missing word(s) in the following sentence... The purpose of the Closing a Project process is to provide a fixed point at which acceptance for the [?] is confirmed.
A. Final project cost
B. Project product
C. Project scope
D. Project mandate
What is a purpose of the Closing a Project process?
A. Provide a fixed point at which acceptance for the project product is confirmed
B. Enable the Project Board to review the success of the current stage
C. Assign work to be done and monitor such work
D. Enable the organization to understand the work that needs to be done to deliver the project's products
According to PRINCE2, which of the following statements is FALSE regarding project closure?
A. A clear end to the project gives recognition that the original objectives have been met
B. A clear end to the project provides an opportunity to ensure that all unachieved goals and objectives are identified
C. A clear end to the project enables the organization to understand the work that needs to be done to deliver the project's products
D. A clear end to the project transfers ownership of the products to the customer
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.