PRINCE2 PRINCE2 Certifications PRINCE2-FOUNDATION Questions & Answers

  • Question 71:

    Which process ensures that plans for achieving the expected benefits are managed and reviewed?

    A. Closing a Project

    B. Initiating a Project

    C. Directing a Project

    D. Starting up a Project

  • Question 72:

    If people other than the Project Board members were doing Project Assurance, who would they report to?

    A. Corporate or programme management

    B. The Project Board member overseeing the relevant area of interest

    C. The Project Manager

    D. The Team Manager whose Work Package execution is being monitored

  • Question 73:

    Which best describes a stakeholder?

    A. Only those people internal to the project team

    B. Anyone that may affect the project

    C. Anyone that can affect, be affected by, or perceive to be affected by an initiative

    D. Someone who has a financial interest/stake in an initiative

  • Question 74:

    Which role does PRINCE2 state would contribute expertise in specialist tools and techniques such as planning and control tools and risk analysis?

    A. Team Manager

    B. Senior Supplier

    C. Project Support

    D. Project Assurance

  • Question 75:

    Which PRINCE2 role is accountable to corporate or programme management for the success of the project?

    A. Project Board

    B. Project Manager

    C. Senior User

    D. Change Authority

  • Question 76:

    Which PRINCE2 role has a specific responsibility for referring to the Project Board if any delegated limits of authority or allocated change budget are forecast to be exceeded?

    A. Team Manager

    B. Project Assurance

    C. Change Authority

    D. Project Manager

  • Question 77:

    Which PRINCE2 role has a specific responsibility for planning, monitoring and managing the team's work?

    A. Senior Supplier

    B. Project Support

    C. Team Manage

    D. Project Manager

  • Question 78:

    Which PRINCE2 role has a specific responsibility for identifying and advising the Project Manager of any issues and risks associated with a Work Package?

    A. Senior Supplier

    B. Team Manager

    C. Project Support

    D. Project Assurance

  • Question 79:

    Which PRINCE2 role has a specific responsibility for briefing non-technical management on supplier aspects of the project?

    A. Team Manager

    B. Project Manager

    C. Senior Supplier

    D. Team member

  • Question 80:

    Which PRINCE2 role has a specific responsibility for managing the information flows between the directing and delivering levels of the project?

    A. Project Manager

    B. Project Support

    C. Team Manager

    D. Senior User

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.