  • Question 61:

    Which process ensures that provision has been made to address any open issues of risks, with follow-on action recommendations?

    A. Closing a Project

    B. Controlling a Stage

    C. Directing a Project

    D. Initiating a Project

  • Question 62:

    In which process would the directing level of management ensure there is continued business justification?

    A. Directing a Project

    B. Managing a Stage Boundary

    C. Initiating a Project

    D. Controlling a Stage

  • Question 63:

    Which process would review the performance of the project against its baselines?

    A. Initiating a Project

    B. Closing a Project

    C. Managing Product Delivery

    D. Starting Up a Project

  • Question 64:

    Which process provides an opportunity to ensure that all unachieved goals and objectives are identified?

    A. Initiating a Project

    B. Controlling a Stage

    C. Directing a Project

    D. Closing a Project

  • Question 65:

    Which process covers the activities of those at the level of management above the Project Manager?

    A. Controlling a Stage

    B. Managing a Stage Boundary

    C. Directing a Project

    D. Managing Product Delivery

  • Question 66:

    Which process starts on completion of the Starting up a Project process?

    A. Controlling a Stage

    B. Directing a Project

    C. Initiating a Project

    D. Managing a Stage Boundary

  • Question 67:

    What is an objective of the Directing a Project process?

    A. Enable the Project Board to be accountable for the project's success

    B. Verify user acceptance of the project's products

    C. Ensure the host site is able to support the products when the project is disbanded

    D. Ensure there is authority to deliver the project's products

  • Question 68:

    What is an objective of the Directing a Project process?

    A. Enable the Project Board to be accountable for the project's success

    B. Ensure that corporate or programme management has an interface to the project

    C. Enable the Project Manager to be accountable for the project's success

    D. Ensure there's a common understanding of how project progress will be monitored and controlled

  • Question 69:

    What is a purpose of the Directing a Project process?

    A. Enable the Project Board to be accountable for the project's success

    B. Establish solid foundations for the project

    C. Enable the Project Manager to be accountable for the project's success

    D. Assign work to be done and monitor such work

  • Question 70:

    In which process may a premature close of the project be authorized?

    A. Directing a Project

    B. Controlling a Stage

    C. Managing a Stage Boundary

    D. Closing a Project

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.