How does PRINCE2 ensure that the specific management needs of an organization are met?
A. By incorporating tailoring
B. By mandating training
C. By focusing on viability
D. By representing best practice
What is an advantage of applying the 'manage by stages' principle?
A. The PRINCE2 method can be used for any type of project
B. The project delivers benefits that are aligned with strategic objectives
C. The project has decision points so that it does not run on in an uncontrolled manner
D. Tolerances can be defined for delegated authority
As a minimum requirement for applying the risk theme, what must specifically be assessed?
A. Whether a risk may cause the project to exceed its cost tolerance
B. Whether a risk may affect the project-level quality tolerances
C. Whether a risk may impact the underlying technical assumptions
D. Whether a risk may alter the project's business justification
What is an advantage of applying the 'learn from experience' principle?
A. It allows the project board to delegate cost tolerances to the project manager
B. It allows the project team to fully understand their roles and responsibilities
C. It allows the project manager to delegate time tolerances to the team managers
D. It allows the project team to identify improvements to be made during the project
Which is a minimum requirement when applying the business case theme?
A. To specify the solution to be used to deliver the business option selected
B. To ensure the corporate business plan is updated with the project costs and benefits
C. To define the management actions required to ensure the project's outcomes are achieved
D. To integrate the benefits management approach with the project and stage plans
Which is a minimum requirement for applying the quality theme?
A. To define the project's approach to quality control
B. To undertake independent audits of the project throughout the project
C. To apply the recommended quality review technique
D. To define the project's approach to quality assurance
Which product describes the method the project will use to engage with corporate, programme management or the customer?
A. Quality management approach
B. Communication management approach
C. Change control approach
D. Benefits management approach
Which is one of the six aspects of project performance to be managed?
A. Efficiency
B. Timescales
C. Estimate
D. Work
Which role is responsible for appointing the senior user in a project that is independent from a program?
A. The project manager
B. The executive
C. Corporate, program management or the customer
D. Project assurance
Which product identifies how often stakeholders require information?
A. Communication management approach
B. Lessons report
C. Configuration item record
D. Benefits management approach
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.