Which product defines how the project board should approve the management products produced during the 'initiating a project' process?
A. Communication management approach
B. Quality management approach
C. Project plan
D. Initiation stage plan
Which is a purpose of the 'identify the risks' step within the recommended risk management procedure?
A. To identify responses to risks documented in the business case
B. To identify information about the project environment and objectives
C. To identify the roles to be involved in risk management activities
D. To identify uncertainties that may impact on the delivery of the project objectives
According to PRINCE2, which characteristic is necessary for an effective project board?
A. An ability to delegate
B. An attention to detail
C. A calm management style
D. A 'problem-solving' approach
Which is an objective of the 'directing a project' process?
A. To review and approve a project mandate
B. To ensure corporate or programme management has an interface to the project
C. To define how risks, issues and changes will be managed
D. To obtain approval for completed products
According to the 'defined roles and responsibilities' principle, what must be represented in the project management team?
A. Project board, project manager and project assurance roles
B. Directing, managing and delivering levels
C. Business, user and supplier interests
D. Corporate, programme management or the customer parties
What must a PRINCE2 project demonstrate?
A. Application of PRINCE2 principles
B. Application of proper leadership skills
C. Application of the activities in each process
D. Application of tools appropriate for the industry
Which is a minimum requirement for applying the risk theme?
A. Threats must be assessed for their impact on the viability of the project
B. A single role that is responsible for all risks must be defined
C. The PRINCE2 risk management procedure must be followed
D. Team managers must maintain their own risk registers
Which is a minimum requirement for applying the organization theme?
A. To document the project management team structure
B. To define the experience required for each project role
C. To include external stakeholders on the project board
D. To train project team members in the use of PRINCE2
What may be funded from a risk budget?
A. Corrections required due to off-specifications
B. Impact analysis of requests for change
C. Implementation of a fallback plan
D. Preparation of the risk management approach
Which approach must be followed as a minimum requirement for applying the plans theme?
A. Activity-based planning
B. Product-based planning
C. Agile
D. Risk management
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.